I am a new user so my experience is limited. Here is the problem I am having. I have projects tasks set up from 1/1/2008 to 12/31/2008. When I print preview a Gantt chart, it only shows me ...
I need a simple Gantt chart with [ProjectName], [StartDate], [EndDate], [%Completed] and a Today's date pointer so that I'll know where I stand. I don't have any sub tasks on the project, it's...
Hello Project Server gurus,
i have a serious problem, yesterday we try to restore the full farm back of main prodcution envrinoment to our development envirnoment. Its restore the suceesful...
I have a sharepoint site setup for my clients using Sharepoint Services 3.0.
My Development team has sent me a mpp file, but I do not have Microsoft Project nor does the client. Si I need ...
My project spans from now until Sept '09.
I want to print the project so the gantt chart only displays from now until the end of fiscal year (Mar 31, 09).
I also want to restrict how m...
I installed Project Server 2007 on Windows server 2003, which already have SharePoint 3.0 installed and configured. I created a new web application with administrator user name and also create...
Can someone please let me know how can I specify a weekday as a holiday in MS Project so that that day is not considered while assigning timelines to resources.
I have a list of jobs in an access database with start and completion dates - I am looking to create a Microsoft Project to display the list of jobs and show the gantt chart part.
Appreciat...
We have a custom enterprise field called "_MITRE Milestones SR Notes". I have that field in project web access but its also in a view within Microsoft Project Professional. I'm trying to pull ...
The Microsoft Access database engine stopped the process because you and another user are attempting to change the same data at the same time. (Error 3197)
hello there
we have files in P3 format for Primavera . but we want to open them thru MS project . is there any soultion to convert the P3 files to MPP files or open it thru MS projects ?
...
How to include weekends on project duration?
I am creating a gantt chart and total project duration shows excluding the weekends. I need to get the total duration count.
Lets say, on Pr...
When trying to access Project Web Access (PWA) site https:, receiving Access Denied message. This also occurs when trying to login with any domain or local admin account. Receiving Applicati...
Scenario: I have deployed Office Enterprise Edition 2007 over LAN with SMS 2003. First I have customized Office with OCT and then deploy it with SMS 2003. Now I want to deploy MS Project Pro 2...
I have a Project Server 2007 setup and recently created Timesheet Period for current month. There were some active tasks for this month and it autopopulated the hours based on the percent com...
I created a PPS 2007 environment and successfully migrated the database over from UMT 3.3 and ran the migration scripts to bring the database from UMT 3.3 --> PPS 2006 --> PPS 2007.
Nobody ...
I have a task with a duration of 1 day that keeps being split over 2 days. I have my calander set so that resources work a 10 hour day from 7am - 5pm (no break). However when I put in a task a...
I need your help, in Office Project serevr Deployment plan. I want to move the existing small farm envirnoment to medium scal farm e.g 2 servers to 5 server farm.
I have 2 option tell me whi...
I have been told that the default assignment owner and the assignment owner could be two different users. Now it seems that there is only one assignment owner field in the assignment record. S...
I've worked with network view and don't see any real advantage to using it over Gantt. It doesn't reflect start-start tasks and other features as well as Gantt shows.
Am I nuts? Why use ...
I need a way to do several things in MS Project; 1. export the tasks and percentage complete that are occuring for the upcoming week 2. allow the user to update the spreadsheet 3. A nice to ha...
L.S.
We´ve received a file with .pp extension, that is supposed to be a MS Project-document, however, it won´t open in MS Project 2003. The error says the file is made in an earlier version o...
Hi Experts:
I am new to Project server 2007 and i am working to create a text file from the Project server Database with some fields in it. The fields contain Different Projects with differen...
Error Type:
Microsoft VBScript compilation (0x800A0411)
Name redefined
/sarTeacher/connection/connector.asp, line 2, column 6
const TBL_ULOGIN = "tbl_UserCT08"
-----^
When I ask for a 25% lag or lead time, how is this computed when you're dealing with whole days?
Technically, some of these computations should move a task into the MIDDLE of a day or the fir...