Advertisement

04.22.2008 at 09:23AM PDT, ID: 23343584
[x]
Attachment Details
[x]
The Solution Rating System

With so many solutions, how can you tell which solutions are most likely to help you and which ones are not? To provide you with a tool to use, we rate our solutions based on various elements that most accurately determine if a solution is a quality solution. To explain what factors affect the solution rating, here are the elements we take into consideration when formulating our solution rating.

  • The Grade of the Solution
  • The Zone Rank of the Expert Providing the Solution
  • The Number of Author and Expert Comments
  • The Number of Experts Contributing
  • The Feedback of the Community

Your Input Matters
Because of the way the system is set up, the most important variable in this equation is you. As a member of Experts Exchange, you are able to cast your vote on the quality of the solutions in regard to how complete, accurate, helpful and easy to understand each solution is. When you provide your feedback, each rating is adjusted accordingly. So, if you see a solution that has a poor rating that you think is a good solution, let us know by rating it. As you do, the rating will be adjusted and will become more accurate for other members of our site.

If you have any suggestions that you would like to make for our rating system, please ask a question in the Suggestions Zone of Community Support.

Thank you!

9.9

Calculating difference between two Dates and times, with other factors.. bit of a pain

Asked by NiCkO in Microsoft Excel Spreadsheet Software, Microsoft Office Suite, Visual Basic Programming

Tags: , ,

Hi.

Bit of a pain this.  But I can do nothing about the format of the data that is imported.  Here goes.

B1 = 10/03/2008 (start date)
C1 = 11:05 (Start Time)
D1 = 12/03/2008 (End Date)
E1 = 14:13 (End Time)

I need it to calculate how long it has taken (in days, and hours or maybe just days with a decimal place, ie 2.1 days)

The conditions it needs to have are that its able to work out NETWORKDAYS and also bank holidays, I have my bank holiday details in cells Totals!F2:F9.

I am really struggling for a calculation that will work, I've been searching for the past 2 days :(

Any Ideas Guys?
Start Free Trial
[+][-]04.22.2008 at 09:39AM PDT, ID: 21412897

View this solution now by starting your 7-day free trial. Setting up your free trial is quick, easy, and secure. We will return you to this solution, unlocked, when you're done.

 

About this solution

Zones: Microsoft Excel Spreadsheet Software, Microsoft Office Suite, Visual Basic Programming
Tags: microsoft, excel, 2000
Sign Up Now!
Solution Provided By: matthewspatrick
Participating Experts: 2
Solution Grade: A
 
 
 