Advertisement

Experts have come up with some helpful tips for getting a solution to your problem fast.

 

Welcome! If you have any general questions about Experts Exchange, feel free to ask me.

 
Time Tested MS Project Solutions: 201 - 225 of 284
 
We are planning to use MS Project corporate-wide to manage projects. As part of a roll-out workgroup that I chair, I am tasked with assisting folks who are not comfortable with MS project t...
I'm getting this error when I add an Issue on the Project's PWA site.  I'll submit the addition and that alert prompt will come up and I hit OK, but somehow it adds the issue to the db.  I'm n...
Like a complete idiot I was working on a large task list in Microsoft Project.  I didn't "save" the project as I should have, and when I returned to work this morning, there had been a power f...
What am I doing wrong when the higher task totals are not caluclating for both the baseline and Work Hrs. I have tried various methods of assigning task, Finish-to-STart types, add and remo...
ms project 2007 i have a task job oriented, workload: 80 hours i assigne 2 ressources, at 50% (r1 and r2) duration: 16 days i change the % units assigned to r2 from 50% to 100% durati...
One of my users is getting the following error message: The project server database is unavailable   You can't access the database for one of the following reasons: There is a problem w...
I have a client with Project 2003 (Win XP). He said all his options seem different than when he used it before but he only uses it a few times a year. I compared his options with a coworkers a...
I have recently added a new user to the AD and included them in all of the appropriate Project Security Groups (Team Members in this case). This Resource shows up as a user in Project Web, but...
I have hided a task accidentally, and I don't find how unhided this task.  How can I unhide the task?
Hi, I'm trying to import quite a few records in the UserData table in the sharepoint database. There's a field tp_GUID, how to I create the value for this field. Actually these record...
Hi, I needed some general help with some follow up: I've always been taught to set up my schedule in "entry view," track actual progress in "tracking view," and view where my project is go...
Hi, i'm trying to update the Tasks Table and i'm getting the error "Missing SELECT keyword", this is my code:  projConn = new OleDbConnection(@"Provider=Microsoft.Project.OLEDB.11.0;PROJECT...
I would like to build reports in Crystal Reports XI with Ms-Project 2007 Data. Does any one here have an idea how to make it possible Thanks Greg
I have a project schedule and have to export the estimated hours by week (7/7/08 - 7/20/08 for example) for a report (S-Curve). How would I export the hours by week or date range? I have the d...
When using the PSI Statusing.SetAssignmentWorkData web service to update the actual work hours of an assignment, is it required to use impersonation (to update data for a set of users) - if th...
Hi guys, i am little confused and trying to find solution over microsft web but didnot get it properly. I have a Microsoft Office Project server 2007 & Project Professional 2007 licence fo...
I am having an issue with saving my schedules to the Project Server. It is taking well into 3 to 5 minutes to complete the process. Now, I've checked the "My Que Jobs" option in Project Web Ac...
I have a sheet with columns:   Cost, Cost1, Cost2, and Cost3 How do I make Cost3 = Cost + Cost1 + Cost2 Please provide step-by-step to keystrokes.  Project doesn't work like Excel.
We are looking to purchase licenses for Project 2003. Is there a way to purchase 5 floating licenses. We would like to have it set up so that the software is installed on our server and that m...
I'm currently running project web server 2003 and get this error  (JSript runtime error 800a01fb.../projectserver/library/localizedstrings.asp, line 78) when I go to "issues" --> "modify colum...
Hi all, I have been asked to help one of our project managers better manage their resources.  Currently they put their tasks/people into an Excel spreadsheet in order to manage them.  Natural...
Hi, I'm use Project Server 2003 with SP2a and SQL 2005 SP2, When I rebuilt the OLAP cube I recibe the followed status: Current Cube Status The cube scheduled to be built on 05/12/20...
We have MS Project Server 2003 SP1 installed on a Windows 2003 SP1 box. On the virtual directory, we have anonymous and Integrated Authentication checked. Most of our users are able to login a...
In Project 2003, I want to create a hyperlink to a bookmark within a Word 2003 document. However, when I choose the file and then click the "Bookmark..." button on the righthand side of the hy...
hi all im practicing installing 2003 project server on a server off the network. i have installed SQL Server on that server and created a SQL DB called 2003project and now in trying to inst...