Your duration for the first task has changed. You went from 25.37 days to 26 days when changing from 41 to 40 percent. Esentially adding roughly 6 hours to the time needed to complete the task. This is what caused your start day to move from Wenesday in the original to Thursday in the revisied.
Even so, I would have thought Friday for your end date. At 40% (the highest allotment in the second task) that resourdce can devote roughly 195 minutes per day to completing the task. So it will take parts of two days to complete.
Defi0 has a good suggestion to look in the resource usage view to see how the time is divided for that task. Also go to your Resource sheet and see if any of your resources show up in red. That will tell you that they are over-allocated somewhere.
Main Topics
Browse All Topics





by: defi0Posted on 2009-10-27 at 02:04:14ID: 25670299
Are you using automatic resource levelling? If so, you may want to check the resource usage of the various resources you've assigned to task 74.
If not, this definitely looks like a bug (MS Project has several issues with multiple part-time resource assignments, you may have run into one).
Have you tried modifying very slightly the effort on task 74?