Project Server 2003: can't adjust actuals or change any working time

Asked by sqlagent007 in Project Management Software, Microsoft Project Project Management Software, Project Management

Tags: Microsoft, Project Server, 2003

Where do I make updates or change information that can be displayed in the adjust actuals or view resource assignments web pages of PWA?

I have a project names Tproject. This project only has 1 task with me assigned to it. I have went into Project Professional connected to the project server, updated my task as 100% complete. (It even shows a blue check mark next to the task)

However now when I navigate through PWA, and go to the resource center, then select adjust actuals I do not see my task as 100% complete, nor can I adjust the actual time.

I cant adjust actuals on any project at all

Any idea what I am doing wrong?
Start Free Trial
[+][-]07.04.2008 at 12:31PM PDT, ID: 21934545

Experts Exchange has a courteous staff of administrators who help members get the most out of the website by means of administrative comments like this one.

Start your 7-day free trial to view this Administrative Comment or ask the Experts your question.

 
[+][-]07.04.2008 at 05:32PM PDT, ID: 21935369

At Experts Exchange, members can ask their questions to thousands of technology professionals, also known as Experts. Experts compete and collaborate to answer those questions by leaving comments like this one.

Start your 7-day free trial to view this Expert Comment or ask the Experts your question.

 
[+][-]07.07.2008 at 07:25AM PDT, ID: 21945277

Often, when Experts are collaborating with members who have asked questions, they will request additional information about the problem. Askers respond with an author comment like this one.

Start your 7-day free trial to view this Author Comment or ask the Experts your question.

 
[+][-]07.07.2008 at 09:26AM PDT, ID: 21946433

Often, when Experts are collaborating with members who have asked questions, they will request additional information about the problem. Askers respond with an author comment like this one.

Start your 7-day free trial to view this Author Comment or ask the Experts your question.

 
[+][-]07.07.2008 at 10:19PM PDT, ID: 21951099

Often, when Experts are collaborating with members who have asked questions, they will request additional information about the problem. Askers respond with an author comment like this one.

Start your 7-day free trial to view this Author Comment or ask the Experts your question.

 
[+][-]07.08.2008 at 10:38AM PDT, ID: 21956126

View this solution now by starting your 7-day free trial. Setting up your free trial is quick, easy, and secure. We will return you to this solution, unlocked, when you're done.

 

About this solution

Zones: Project Management Software, Microsoft Project Project Management Software, Project Management
Tags: Microsoft, Project Server, 2003
Sign Up Now!
Solution Provided By: sqlagent007
Participating Experts: 1
Solution Grade: B
 
 
[+][-]07.08.2008 at 10:39AM PDT, ID: 21956135

Often, when Experts are collaborating with members who have asked questions, they will request additional information about the problem. Askers respond with an author comment like this one.

Start your 7-day free trial to view this Author Comment or ask the Experts your question.

 
[+][-]07.09.2008 at 02:49AM PDT, ID: 21961824

Experts Exchange has a courteous staff of administrators who help members get the most out of the website by means of administrative comments like this one.

Start your 7-day free trial to view this Administrative Comment or ask the Experts your question.

 
 
Loading Advertisement...
20080716-EE-VQP-32 / EE_QW_2_20070628