I am trying to install the add-in into Outlook 2003 but getting: [The language of the project addin must match the language of Outlook...] The project server is EN-US but all Outlook clients...
In testing various project plans in MS Project Server 2007, weve found that the Work numbers on the Resource Usage view arent correct for the other projects on the server.  Ive done some ...
Hi experts, I am having a problem synchronizing workspaces in PWA. I go to PWA>Server Settings>Project Workspaces and when i synchronize any site, it gives me the errors below. The first th...
Hi! We recently deployed a trial version of MS Project 2007 Server for evaluation. The server was deployed in a stand alone server configuration. Server had one Local IP address and one publi...
How does MS Project calculate BCWP?  Its not as simple as %work complete * budgeted hours anymore.
I downloaded the Project 2007 trial so I could test it out, and begin working on a project while I wait for my "real" version to come in the mail.  I started working on a project file, and got...
I'm just getting familiar with MS-Project.   I have a simple question about allocating resources in the software. Let me provide an easy example (see snippet below): Summary: As subtask...
I need to export resource usage data for multiple projects to Excel to be used in a pivot table.  Im aware of the TimeScaleData Method but it appears that this method works on a single projec...
Hi. I have a query regarding how to set up project server team assignments. As far as I understand it, team assignments allow team members to "self-assign" work. All well and good. What I'd li...
Hi, I am trying to assign overtime to resources in microsoft project 2003.  Is there a way I can set overtime hours in a calendar or do I need to assign it elsewhere in the program.  Basically...
My company is running Sharepoint 2007 and Project Server 2007. I did the following in an attempt to move my company's project databases from one SQL Server to another: 1. Backed up the whol...
Hi for everyone, I need help, this is my error, this happen when I save some resource from my PS, this resource has a custom fields assosiations. Any IDEA??????? LOG Error summary/are...
I'm using MS Project 2007 to track a project. I have a 240 hour fixed-work task that has a start date of 4/7/08 and end date of 5/16/08. No work has begun on the task - actual start is NA an...
In MS Project 2000, how do you enter an early start/finish date or late start/finish. I've added the column, but it's display only. What's up?
Hi, I am searching for script or some kind of interface which allows Windows Sharepoint service/Shapoint Portal users to reset their passwords when they forget their current passwords. This...
Would anyone know of a good resource to dowmload some Sharepoint 2007 Templates. There were a bunch for 3.0 but have yet to see that many for 2007. Thanks in Advance.
I need your help, in Office Project serevr Deployment plan. I want to move the existing small farm envirnoment to medium scal farm e.g 2 servers to 5 server farm. I have 2 option tell me whi...
Is there such a thing as a free ms project style, gnatt chart online.  Perhaps something similar to to what google docs and zoho has for other types of documents?  I love the little pluses + a...
I need a simple Gantt chart with [ProjectName], [StartDate], [EndDate], [%Completed] and a Today's date pointer so that I'll know where I stand. I don't have any sub tasks on the project, it's...
Hi, Is is possible to create a mpp file through C#. Can you point me to the urls? Thanks
Hi Experts, Problem: I would like to assign a fixed yearly cost to a resource in MS Project. Ok, I have a core bunch of developers who will be developing day by day on 2 large and comple...
Let me apologize in advance if the answer is simple and is right in front of my face, but I can't find it. Is there a way in Project 2007 to either Highlight tasks that are past due or prin...
I have a split situation. At work I use MS-Project 2007 and at home 2003. To ensure transportability filers are always saved in 2003 MPP formats. However when I save files from 2007 they a...
We have successfully deployed Microsoft Office Project Server 2007 on our server.  I've setup users and groups to each project and everyone has configured the alerts options to receive an em ...
Hello, I have PWA working fine from within my network, but can't get it to work from over the internet.  I would like my end users to be able to access the Project Web Access sharepoint site ...