Jeff,
You can also accomplish this with the split task function. There is a button on the toolbar next to link and unlink that allows you to split a task into pieces and move the pieces further out without adding to the continuous duration of the task.
For example take a 15 day task and break it into three 5 day chunks. Each of those pieces can then be spread out further accross the schedule as needed.
Bob brings up an important point about distinguishing between work and duration. If you have thees three 5 day pieces and you placed them say on Oct 1-5, November 1-5 and December 1-5, there is only 15 days of work but the duration will show as roughly 65 days. As duration is the time elapsed from start to finish of a task.
Splitting the task however will make sure that the work assigned to the resource which can be viewed in the resource usage view is accurate for each task
Main Topics
Browse All Topics





by: bobsegrestPosted on 2008-10-09 at 04:18:46ID: 22677164
Hello Jeff,
Duration and work are separate things in Microsoft Project and I suspect with a little guidance it can be used to provide a more accurate model of your effort.
Your description almost sounds like you have a one task project plan. If this is the case, it may be necessary to break each project (request) into a few more tasks. For example, your task list may need to be something more like:
Request Submitted
Provide Estimate
Perform Initial Tests
Perform Final Tests
Deliver Test Results
It is almost always a bad practice to model "waiting for something to happen" as a task. Project allows you to define a lag between tasks or the definition of a constraint ("start no earlier than" for example) to model this sort of zero effort delay in a project.
Please zip one of your project (mpp) files and attach it to this discussion topic. This will give us a better picture of your current plan and provide a base for more specific feedback and guidance.
It is also a good idea to tell us what version of Microsoft Project you are using and whether or not you are using a Project Server each time you ask a new question. Sometimes the answers or at least the examples offered need to be version specific.
Bob Segrest, PMP
MCITP, Microsoft Project Blackbelt