slipping tasks

folks

in Microsift project how do I show a task with its orinal date and then the slipped actual date in the gantt chart

Rutger
0
rutgermons
Asked:
rutgermons
1 Solution
 
dbase118Commented:
Once you have completed the Project Planning, you will want to save a baseline. Baseline represents the best guess estimate of the project's progression. Go to Tools....Tracking....Save baseline. Select the options to Save baseline for entire Project. Then you can either use the tracking Gantt view to show baseline vs actual. Or you can use the Gantt chart wizard to format your regular Gantt. I would personally just recommend using your tracking Gantt since it is already done for you.

Is this what you are looking for?
0

Featured Post

[Webinar] Cloud and Mobile-First Strategy

Maybe you’ve fully adopted the cloud since the beginning. Or maybe you started with on-prem resources but are pursuing a “cloud and mobile first” strategy. Getting to that end state has its challenges. Discover how to build out a 100% cloud and mobile IT strategy in this webinar.

Tackle projects and never again get stuck behind a technical roadblock.
Join Now