Need help with scheduling shifts in Project!

Posted on 2006-05-10
Last Modified: 2013-11-15
I am trying to schedule two 10 hour shifts in one day.  6am start and 4pm finish (1st shift), 4pm start and 2am finish (2nd shift).  When I go to tools/ change working time and enter the hours I get a message (the end of the shift must be later than the start of the shift).  I have also tried to use the 24 hour schedule for this and receive the same message.  Or the 24 hour schedule will let me put in shifts then when I enter a task that will take 18 hours it goes back to the default settings and spreads the task out over 3 days.

Question by:kevotron
    LVL 35

    Expert Comment

    I think, you have to splitt the second shift into 0-4 am and 4-12h pm

    Usually, you have two calendar in your project, one project calendar for the company (tasks) and one for reosurces.
    The project calendar decribes the working time of the company.
    The resource calendar determines, when a resource is available. You can assign this resource calendar to a resource. Additionall, each resource has its own individual calendar, which describes exceptions from the (default) resource calendar.

    The dayly work is set to 8h by default. If you have a task over 18h, the assigned resource must have a calendar, which allows 18h work a day. If the default clendar is assigned to the resource, the resource is workuing 8h a day = 3 days for 18h (8+8+2)
    LVL 10

    Accepted Solution


    When setting up a shift that spans midnight, pay close attention to the working hours per day, and not just to the shift hours. For example, to set up a shift that runs from 10:00 P.M. to 6:00 A.M. weekdays, enter the following nondefault working times:

    Mondays 10:00 PM to 12:00 AM.
    Tuesdays through Fridays 12:00 AM to 6:00 AM and 10:00 PM to 12:00 AM.
    Saturdays 12:00 AM to 6:00 AM.
    Working times that span midnight are difficult to visualize in the Change Working Times dialog box, but are well illustrated in the Project Working Times side pane.

    The Project Working Times side pane provides an easy way to set the project's working times. On the Project Guide toolbar, click Tasks. Click Define general working times, and then follow the instructions that appear in the side pane.


    Write Comment

    Please enter a first name

    Please enter a last name

    We will never share this with anyone.

    Featured Post

    Do You Know the 4 Main Threat Actor Types?

    Do you know the main threat actor types? Most attackers fall into one of four categories, each with their own favored tactics, techniques, and procedures.

    Re-planning is just as important as planning. MS Project files need to be updated regularly to reflect the current status of the project and to streamline the upcoming tasks. We have seen a lot of issues where project managers have not updated the p…
    "Disruption" is the most feared word for C-level executives these days. They agonize over their industry being disturbed by another player - most likely by startups.
    This video is in connection to the article "The case of a missing mobile phone (". It will help one to understand clearly the steps to track a lost android phone.
    Internet Business Fax to Email Made Easy - With eFax Corporate (, you'll receive a dedicated online fax number, which is used the same way as a typical analog fax number. You'll receive secure faxes in your email, fr…

    760 members asked questions and received personalized solutions in the past 7 days.

    Join the community of 500,000 technology professionals and ask your questions.

    Join & Ask a Question

    Need Help in Real-Time?

    Connect with top rated Experts

    6 Experts available now in Live!

    Get 1:1 Help Now