Solved

Need help with scheduling shifts in Project!

Posted on 2006-05-10
2
Medium Priority
?
419 Views
Last Modified: 2013-11-15
I am trying to schedule two 10 hour shifts in one day.  6am start and 4pm finish (1st shift), 4pm start and 2am finish (2nd shift).  When I go to tools/ change working time and enter the hours I get a message (the end of the shift must be later than the start of the shift).  I have also tried to use the 24 hour schedule for this and receive the same message.  Or the 24 hour schedule will let me put in shifts then when I enter a task that will take 18 hours it goes back to the default settings and spreads the task out over 3 days.

0
Comment
Question by:kevotron
2 Comments
 
LVL 35

Expert Comment

by:Bembi
ID: 16653047
I think, you have to splitt the second shift into 0-4 am and 4-12h pm

Usually, you have two calendar in your project, one project calendar for the company (tasks) and one for reosurces.
The project calendar decribes the working time of the company.
The resource calendar determines, when a resource is available. You can assign this resource calendar to a resource. Additionall, each resource has its own individual calendar, which describes exceptions from the (default) resource calendar.

The dayly work is set to 8h by default. If you have a task over 18h, the assigned resource must have a calendar, which allows 18h work a day. If the default clendar is assigned to the resource, the resource is workuing 8h a day = 3 days for 18h (8+8+2)
0
 
LVL 10

Accepted Solution

by:
harisrashid earned 1000 total points
ID: 16680384
hi,

When setting up a shift that spans midnight, pay close attention to the working hours per day, and not just to the shift hours. For example, to set up a shift that runs from 10:00 P.M. to 6:00 A.M. weekdays, enter the following nondefault working times:

Mondays 10:00 PM to 12:00 AM.
Tuesdays through Fridays 12:00 AM to 6:00 AM and 10:00 PM to 12:00 AM.
Saturdays 12:00 AM to 6:00 AM.
Working times that span midnight are difficult to visualize in the Change Working Times dialog box, but are well illustrated in the Project Working Times side pane.

The Project Working Times side pane provides an easy way to set the project's working times. On the Project Guide toolbar, click Tasks. Click Define general working times, and then follow the instructions that appear in the side pane.

Regards,
Haris
0

Featured Post

Free Tool: Site Down Detector

Helpful to verify reports of your own downtime, or to double check a downed website you are trying to access.

One of a set of tools we are providing to everyone as a way of saying thank you for being a part of the community.

Question has a verified solution.

If you are experiencing a similar issue, please ask a related question

At the office, we’ve started to get serious about organizing what we’re doing. I mean, it was getting to the point where every time I received a phone call, it began with “I know you’re really busy, but…” My boss was taking tasks away from me left a…
Learn how ViaSat reduced average response times for IT incidents from 10 minutes to 30 seconds.
Is your data getting by on basic protection measures? In today’s climate of debilitating malware and ransomware—like WannaCry—that may not be enough. You need to establish more than basics, like a recovery plan that protects both data and endpoints.…
As many of you are aware about Scanpst.exe utility which is owned by Microsoft itself to repair inaccessible or damaged PST files, but the question is do you really think Scanpst.exe is capable to repair all sorts of PST related corruption issues?
Suggested Courses

810 members asked questions and received personalized solutions in the past 7 days.

Join the community of 500,000 technology professionals and ask your questions.

Join & Ask a Question