Change Standard Calendar

Posted on 2006-11-08
1
247 Views
Last Modified: 2013-11-15
Is it possible to change the standard calendar to reflect public holidays.  Each time  I create a new project I ave to go in and enter the public holidays as non work time, it would make sense if I could set this somewhere and have it automatically default in for all new projects.

Any ideas??

thanks

Ben
0
Comment
Question by:Ben_A_Boyd
[X]
Welcome to Experts Exchange

Add your voice to the tech community where 5M+ people just like you are talking about what matters.

  • Help others & share knowledge
  • Earn cash & points
  • Learn & ask questions
1 Comment
 
LVL 5

Accepted Solution

by:
sinjin earned 250 total points
ID: 17917926
yes.... it's a two phase process.
1) Create a calendar that reflect the public holidays, etc
Open a new blank project file...
Tools, Change Working Time
Click on 'New' at the bottom of the dialog... I would suggest you create a copy of Standard and name it "Standard With Holidays" or something.
Make Required Changes.

2) Copy that calendar in the "Global.mpt" file -- that's the default template for a blank project.
While in your project file that has your brand new calendar in it ...
Tools, Organizer.
Select the 'Calendars' tab
Copy the new calendar into the global.mpt.

Now, when you create a new blank project you can reference that new calendar as you need to in Project, Project Info.

Luck,
 - sinjin

0

Featured Post

Announcing the Most Valuable Experts of 2016

MVEs are more concerned with the satisfaction of those they help than with the considerable points they can earn. They are the types of people you feel privileged to call colleagues. Join us in honoring this amazing group of Experts.

Question has a verified solution.

If you are experiencing a similar issue, please ask a related question

At the office, we’ve started to get serious about organizing what we’re doing. I mean, it was getting to the point where every time I received a phone call, it began with “I know you’re really busy, but…” My boss was taking tasks away from me left a…
"Disruption" is the most feared word for C-level executives these days. They agonize over their industry being disturbed by another player - most likely by startups.
Monitoring a network: how to monitor network services and why? Michael Kulchisky, MCSE, MCSA, MCP, VTSP, VSP, CCSP outlines the philosophy behind service monitoring and why a handshake validation is critical in network monitoring. Software utilized …
This tutorial will teach you the special effect of super speed similar to the fictional character Wally West aka "The Flash" After Shake : http://www.videocopilot.net/presets/after_shake/ All lightning effects with instructions : http://www.mediaf…

630 members asked questions and received personalized solutions in the past 7 days.

Join the community of 500,000 technology professionals and ask your questions.

Join & Ask a Question