Change Standard Calendar

Posted on 2006-11-08
1
Medium Priority
?
249 Views
Last Modified: 2013-11-15
Is it possible to change the standard calendar to reflect public holidays.  Each time  I create a new project I ave to go in and enter the public holidays as non work time, it would make sense if I could set this somewhere and have it automatically default in for all new projects.

Any ideas??

thanks

Ben
0
Comment
Question by:Ben_A_Boyd
[X]
Welcome to Experts Exchange

Add your voice to the tech community where 5M+ people just like you are talking about what matters.

  • Help others & share knowledge
  • Earn cash & points
  • Learn & ask questions
1 Comment
 
LVL 5

Accepted Solution

by:
sinjin earned 1000 total points
ID: 17917926
yes.... it's a two phase process.
1) Create a calendar that reflect the public holidays, etc
Open a new blank project file...
Tools, Change Working Time
Click on 'New' at the bottom of the dialog... I would suggest you create a copy of Standard and name it "Standard With Holidays" or something.
Make Required Changes.

2) Copy that calendar in the "Global.mpt" file -- that's the default template for a blank project.
While in your project file that has your brand new calendar in it ...
Tools, Organizer.
Select the 'Calendars' tab
Copy the new calendar into the global.mpt.

Now, when you create a new blank project you can reference that new calendar as you need to in Project, Project Info.

Luck,
 - sinjin

0

Featured Post

[Webinar] Lessons on Recovering from Petya

Skyport is working hard to help customers recover from recent attacks, like the Petya worm. This work has brought to light some important lessons. New malware attacks like this can take down your entire environment. Learn from others mistakes on how to prevent Petya like worms.

Question has a verified solution.

If you are experiencing a similar issue, please ask a related question

Re-planning is just as important as planning. MS Project files need to be updated regularly to reflect the current status of the project and to streamline the upcoming tasks. We have seen a lot of issues where project managers have not updated the p…
Learn how ViaSat reduced average response times for IT incidents from 10 minutes to 30 seconds.
In this video, Percona Solutions Engineer Barrett Chambers discusses some of the basic syntax differences between MySQL and MongoDB. To learn more check out our webinar on MongoDB administration for MySQL DBA: https://www.percona.com/resources/we…
We’ve all felt that sense of false security before—locking down external access to a database or component and feeling like we’ve done all we need to do to secure company data. But that feeling is fleeting. Attacks these days can happen in many w…

719 members asked questions and received personalized solutions in the past 7 days.

Join the community of 500,000 technology professionals and ask your questions.

Join & Ask a Question