Hyperlinks and Notes not showing up in PWA

Posted on 2006-11-13
7
Medium Priority
?
658 Views
Last Modified: 2013-11-15
When adding notes or hyperlinks to a task in Project 2003 we do not see the notes or hyperlinks when we add that to the view in PWA on the users task page?  It just shows up blank, anyone know why that would be?

thanks,
MS
0
Comment
Question by:mschwade
[X]
Welcome to Experts Exchange

Add your voice to the tech community where 5M+ people just like you are talking about what matters.

  • Help others & share knowledge
  • Earn cash & points
  • Learn & ask questions
  • 4
  • 3
7 Comments
 
LVL 1

Author Comment

by:mschwade
ID: 17937790
Some places show the links, some don't.. For example...

Timesheet view on Project Center -- I have the Hyperlink fields, nothing is populated.

If I click on the Project Name in Project Center then it brings up a view with Tasks Summary and those Hyperlink Fields are populated.

What gives? Are these pulling from different db's??  Is there a field that contains the note?

Thanks,
MS
0
 
LVL 1

Expert Comment

by:BoggyBayouBoy
ID: 17973601
try this:

Tools > Customize > Published Fields  

then add the hyperlink field

hit ok and then re-publish
0
 
LVL 1

Author Comment

by:mschwade
ID: 17979147
Nope, theres not even a Notes field to add there.
0
On Demand Webinar: Networking for the Cloud Era

Did you know SD-WANs can improve network connectivity? Check out this webinar to learn how an SD-WAN simplified, one-click tool can help you migrate and manage data in the cloud.

 
LVL 1

Expert Comment

by:BoggyBayouBoy
ID: 17980074
thats odd... the "hyperlink" field should be selectable to add - are you sure its not?
0
 
LVL 1

Author Comment

by:mschwade
ID: 17980124
Hyperlink is, but note is not.
0
 
LVL 1

Accepted Solution

by:
BoggyBayouBoy earned 2000 total points
ID: 17980264
yeah... the note is not one of the "publishable" fields.  

did u check to see if hyperlink is populated on PWA?
0
 
LVL 1

Author Comment

by:mschwade
ID: 17980546
it is not in timesheet view, but is when you click on the Project Name.
0

Featured Post

Hire Technology Freelancers with Gigs

Work with freelancers specializing in everything from database administration to programming, who have proven themselves as experts in their field. Hire the best, collaborate easily, pay securely, and get projects done right.

Question has a verified solution.

If you are experiencing a similar issue, please ask a related question

Article by: x-men
Where used to see Gantt charts for illustrating project timelines, but what if I wanted to visualize passed timed events? Here's how.
Online collaboration is quickly becoming embedded in the workplace, and its benefits are tangible. See what the current landscape looks like and what the future holds for collaboration tools and the future of work.
In this video you will find out how to export Office 365 mailboxes using the built in eDiscovery tool. Bear in mind that although this method might be useful in some cases, using PST files as Office 365 backup is troublesome in a long run (more on t…
In this video, Percona Solutions Engineer Barrett Chambers discusses some of the basic syntax differences between MySQL and MongoDB. To learn more check out our webinar on MongoDB administration for MySQL DBA: https://www.percona.com/resources/we…

715 members asked questions and received personalized solutions in the past 7 days.

Join the community of 500,000 technology professionals and ask your questions.

Join & Ask a Question