Project Management Question - PMP Exam Preparation

I'm studying for the PMP exam doing some practice quizzes when I came across this question:

Based on an approved change, the customer increased the project scope by 65%.  This increased your cost estimate fivefole.  Now you must change the scheduled start and finished dates in your approved project schedule.  Your first step would be to...

A) Rebaseline the schedule
B) Modify the contract
C) Update the schedule baseline
D)  Add resources

I picked 'A' rebaseline the schedule.  The correct answer was 'C' with no real explanation.

I don't understand how the two are different?  And Why is 'C' the correct answer?  

Can I get an opinion from a PM expert?

ASKER CERTIFIED SOLUTION
Avatar of lyonst
lyonst
Flag of Ireland image

Link to home
membership
This solution is only available to members.
To access this solution, you must be a member of Experts Exchange.
Start Free Trial
Also.. You should re-baseline only if the actual project progress has little to do with the original baseline, and in this case this is not a vaid assumption.
Avatar of tmonteit

ASKER

Thanks!!!
No Problem.. Thanks.

Best of luck with the exam and studies.. Let me know if you have any other questions..