Solved

Planned Hours vs Actual hours

Posted on 2007-11-27
3
1,623 Views
Last Modified: 2013-11-15
Here is what I want to accomplish.  I have sub tasks the roll up to a task.  Here is what I want to capture

1. Start and Finish is ESTIMATED
2. I want to estimated the hours to completed each subtask
3. I want to enter the actual hours the task took.
4. I want to show our estimated hours compared to our actual (WORK vs ACTUAL WORK)

We can have a task that could span 1 month to complete BUT the hours estimated could be 8 and the actual hours to complete may be 4

What I'm seeing is if I indicate a sub task is 100% complete and it has estimated 1hr with the actual of 30 min, the Actual Work changes to match the estimated of 1hr.

This defeats the purpose of my objective.

How do I get around this?
0
Comment
Question by:keschuster
  • 2
3 Comments
 
LVL 13

Expert Comment

by:jbfraser
Comment Utility
Instead of changing percent complete to 100%, set the remaining work to zero. This will reduce the Work field to be the same as Actual Work and make the task 100% complete. You may want to add the remaining work column to your view.

In your process, you are not really telling Project that your value for work was not correct, you are telling Project that all that work was done.


James Fraser
0
 

Author Comment

by:keschuster
Comment Utility
maybe i need to use these fields in a way I'm not catching on to.  Let me reiterate what I'm trying to accomplish

I have a task that I "budget" 10 hours for
Duration of the task WILL span 3 months
The actual time worked to complete the task is 5 hours.

At the end of the day I want to report that we expected to use 10 hrs , it only took 5hrs

How do I set that up?
0
 
LVL 13

Accepted Solution

by:
jbfraser earned 500 total points
Comment Utility
I think I understand.
The MS Project way to do what you are describing is to use the baselines. Set Work to 10 hours, Duration to 3 months. Save a baseline.

Fill in actual work. Use a timephased view if needed to track when the work happened, or just set the dates / duration appropriately.

Set remaining work to 0 or set Work to equal Actual Work (Same thing really.)

The reason to use the baselines is that in Project, % Work Complete is always Actual Work / Work. So if you want 100% complete, they must be equal.


Does that help?
0

Featured Post

Highfive Gives IT Their Time Back

Highfive is so simple that setting up every meeting room takes just minutes and every employee will be able to start or join a call from any room with ease. Never be called into a meeting just to get it started again. This is how video conferencing should work!

Join & Write a Comment

At the office, we’ve started to get serious about organizing what we’re doing. I mean, it was getting to the point where every time I received a phone call, it began with “I know you’re really busy, but…” My boss was taking tasks away from me left a…
Article by: x-men
Where used to see Gantt charts for illustrating project timelines, but what if I wanted to visualize passed timed events? Here's how.
In this tutorial you'll learn about bandwidth monitoring with flows and packet sniffing with our network monitoring solution PRTG Network Monitor (https://www.paessler.com/prtg). If you're interested in additional methods for monitoring bandwidt…
You have products, that come in variants and want to set different prices for them? Watch this micro tutorial that describes how to configure prices for Magento super attributes. Assigning simple products to configurable: We assigned simple products…

763 members asked questions and received personalized solutions in the past 7 days.

Join the community of 500,000 technology professionals and ask your questions.

Join & Ask a Question

Need Help in Real-Time?

Connect with top rated Experts

9 Experts available now in Live!

Get 1:1 Help Now