I copied several tasks from one MS Project file into another one, then attempted to renumber the WBS.  However, the WBS renumber feature is greyed out in the Project drop-down.
0
donestes
Asked:
donestes
1 Solution
 
donestesAuthor Commented:
It turns out that there are two answers to this question.  One can go into Tools > Options and check "show outline number" which causes the WBS number to show in the Task Name column where it is also automatically renumbered.

The other, more obscure answer, is that if you want a WBS column with "show outline number" unchecked, then Project > WBS > Define Code and create a default code definition.  Then Project > WBS > Renumber is no longer grayed out.

Completely stupid of course, but that's MS Project.
0

Featured Post

[Webinar] Kill tickets & tabs using PowerShell

Are you tired of cycling through the same browser tabs everyday to close the same repetitive tickets? In this webinar JumpCloud will show how you can leverage RESTful APIs to build your own PowerShell modules to kill tickets & tabs using the PowerShell command Invoke-RestMethod.

Tackle projects and never again get stuck behind a technical roadblock.
Join Now