Assignment Owner vs. Default Assignment Owner - what's the difference?

Posted on 2008-10-10
2
2,659 Views
Last Modified: 2013-11-15
I have been told that the default assignment owner and the assignment owner could be two different users. Now it seems that there is only one assignment owner field in the assignment record. So only one person can provide status (or change status - like actual work) for an assignment record.
If that is true, how does the new default assignment owner field fix the "resource is on vacation" problem?

Bottom line:  does the resource in an assignment always have the power to change its status? even if he is not listed as the assignment owner?
Another way to ask the question - is it possible to set up PS2007 such that two users can actually change 'actuals' status of the same assignment record, or is it limited to just one?

Thanks for your help,
Ken
0
Comment
Question by:kenfhenderson
[X]
Welcome to Experts Exchange

Add your voice to the tech community where 5M+ people just like you are talking about what matters.

  • Help others & share knowledge
  • Earn cash & points
  • Learn & ask questions
2 Comments
 
LVL 13

Accepted Solution

by:
bobsegrest earned 500 total points
ID: 22694185
Hi Ken,

Consider a situation where you have an employee (resource) with no access to the project server.  Perhaps they travel all the time and call someone else in the office (their supervisor  perhaps) to report their status.  Within Project Server you will designate this other person as the Default Assignment Owner for this resource.

When a project manager assigns a task to this resource, the task will be listed in the My Tasks list that belongs to the Default Assignment Owner.  For example if I am the Default Assignment Owner for a resource named Test PM 4, and this resource is assigned Task 5 in Test Project 1, the assignment would be displayed as shown in the attached screenshot.

Note, that the name of the assigned resource (Test PM 4) is listed in the Resource Name column.  

There are a couple of details that you need to pay attention to...

1. Project Server does NOT put a duplicate entry in the My Tasks page for the assigned resource (Test PM 4 in this example).  

2. Changing the Default Assignment Owner does NOT have any impact on assignments that have already been created.

In summary...

The Default Assignment Owner for a resource is the resource (Bob is normally the Default Assignment Owner for Bob).  If an administrator elects to change Bob's Default Assignment Owner to Sam, Bob still does the work, Bob is still the name assigned to the task, but Sam receives the assignment notifications and has to enter the status update.  Communicating the assignment to Bob and getting Bob to report his status is Sam's problem to deal with...

The only person that can change 'actuals' is Sam because Sam is the assignment owner...  (If you are programming, you still have to impersonate Sam...)

Does this help?

Bob Segrest, PMP
MCITP, Microsoft Project Blackbelt
MyTasks.jpg
0
 

Author Closing Comment

by:kenfhenderson
ID: 31597323
Thanks for the clarity!
You're the best!
0

Featured Post

On Demand Webinar - Networking for the Cloud Era

This webinar discusses:
-Common barriers companies experience when moving to the cloud
-How SD-WAN changes the way we look at networks
-Best practices customers should employ moving forward with cloud migration
-What happens behind the scenes of SteelConnect’s one-click button

Question has a verified solution.

If you are experiencing a similar issue, please ask a related question

Article by: x-men
Where used to see Gantt charts for illustrating project timelines, but what if I wanted to visualize passed timed events? Here's how.
Online collaboration is quickly becoming embedded in the workplace, and its benefits are tangible. See what the current landscape looks like and what the future holds for collaboration tools and the future of work.
Monitoring a network: why having a policy is the best policy? Michael Kulchisky, MCSE, MCSA, MCP, VTSP, VSP, CCSP outlines the enormous benefits of having a policy-based approach when monitoring medium and large networks. Software utilized in this v…
Add bar graphs to Access queries using Unicode block characters. Graphs appear on every record in the color you want. Give life to numbers. Hopes this gives you ideas on visualizing your data in new ways ~ Create a calculated field in a query: …

630 members asked questions and received personalized solutions in the past 7 days.

Join the community of 500,000 technology professionals and ask your questions.

Join & Ask a Question