Link to home
Start Free TrialLog in
Avatar of cmwahlstrom
cmwahlstrom

asked on

Task with 1 day duration being split over 2 days

I have a task with a duration of 1 day that keeps being split over 2 days. I have my calander set so that resources work a 10 hour day from 7am - 5pm (no break). However when I put in a task and give it a duration of 1 day its starts the task at 7am on one day but does not finish until 8am the next day. The onyl way I can get it to start at 7am and finish at 5pm on the same day is to put a duration of .9 day (and work of 540 min). I have gotten others task in the project to appear correctly (for the same resource) but it seems I get to a certain point where it just refuses to schedule the work evenly over 1 day. Any ideas why?
Avatar of Patrick Matthews
Patrick Matthews
Flag of United States of America image

Hello cmwahlstrom,

The first thing I would check is whether the task has a dependency on another task lasting less than a day.

Example:

Task 1 starts 10/23 at beginning of day and has duration of, say, 0.75 days
Task 2 has duration of 1 day, and starts on completion of Task 1

In this case, Task 2 will break over 2 days...

Regards,

Patrick
Are there any other custom schedules in your project? It does sound as if whichever day you are working with has only allocated 9 hours of work-time for that given day. I would think it must be something in the calendar definitions that is triggering that . Can you do a capture of your calendar screen with the drop down that shows all calendars?
Avatar of cmwahlstrom
cmwahlstrom

ASKER

All my tasks go for whole days. There are no tasks that go for less then a day. And up until a certain oint in the project the work is being spread evenly over the days. I have attached a screenshot of where it starts to go wrong and also one that shows the particluar calendar being used for the first person it starts to go wrong for. Hopefully his might make it a bit clearer.
Calendar.JPG
project---calendar-issue.JPG
cmwahlstrom,

Task number 66 which you have highlighed has two icons in the information column (Blue I). The top icon is a calendar with a blue square which indicates a date constraint. When you point to the other icon what information pops on your screen. I noticed it was the only task with that second icon, wondering if maybe something got defined there for the task by mistake.
I had switched that task to use the same calendar as the resource (just to make sure everything was using the same calendar). Even when I switch the calendar back to the dfeault of None in the Task Details the same thing happens
ASKER CERTIFIED SOLUTION
Avatar of aflockhart
aflockhart
Flag of United Kingdom of Great Britain and Northern Ireland image

Link to home
membership
This solution is only available to members.
To access this solution, you must be a member of Experts Exchange.
Start Free Trial
Well it would seem that Project was refusing to start the 1st day of some shifts (shifts are typically 4 days long) at 7am but would happily start the second day (and subsequent days) at 7am. It was then also only scheduling 13 or 14 min work for some 15 minute time brackets, so all of this was pushing it over into that extra day. I have manually changed all the tasks in the task usage section to start at 7am and for each resource to work the full 15 minutes for each 15 minute bracket. This seems to have it now appearing as it should. I am just not sure what caused it to do it in the first place. The straneg thing is on some shifts it would work fine yet on other shifts for the same person it wouldn't (yet it would for other resources on the same shift.