Solved

task cannot break overnight or over weekend - must be started/finished on same day

Posted on 2009-04-09
5
665 Views
Last Modified: 2013-11-15
Let's say I have a 6h task duration, and as the plan slides around, I can't have this task scheduled where it starts on one afternoon and finishes the next morning. Let's pretend it's pouring concrete. Is there any way to tell Project that if the plan is ready for this task, but there's only 4 hours left in the business day, to make it start the following morning instead? Appreciate the help!
0
Comment
Question by:nbozzy
[X]
Welcome to Experts Exchange

Add your voice to the tech community where 5M+ people just like you are talking about what matters.

  • Help others & share knowledge
  • Earn cash & points
  • Learn & ask questions
  • 2
  • 2
5 Comments
 
LVL 15

Assisted Solution

by:dbase118
dbase118 earned 50 total points
ID: 24107372
nbozzy,

I hope someone proves me wrong because I would be very interested but I dont think you can have Project  automatically make this determination. Essentially it sounds like you want Project to use a variable for Lag time which it can not do.

Project tries to schedule optimally your resources against available working time to give you the shortest distance between First and last tasks in the project.

You can certainly "hard-code" this lag if you know that a task must be scheduled like this, but as you say when thing start moving around the hard-coded lag may become incorrect to fit the situation.
0
 

Author Comment

by:nbozzy
ID: 24107529
Exactly, dbase118! Can't use a deadline (etc.)  because who knows how the plan will ultimately schedule this task? I'm rather amazed that the folks in Redmond didn't think about this need......or if anyone knows of a solution, I'll be thrilled and so will a lot of other people! Anybody.....????
0
 
LVL 15

Expert Comment

by:dbase118
ID: 24108073
Well,

Its not so much that they didnt think of it , but rather the fact that it kind of goes against the basic philosophy of stright-line scheduling that Project adhere's to.  We all know what happens to those who do not conform to the almight M$.

They would view the kind of process you are looking for as the exception rather than the norm. But most of Project Management is certainly not the norm. Hopefully someone else will chime in as you said. Im certainly interested in this one now as well. I had a similar issue with different circumstances where  I had $1000 a day consultant getting assigned to 6-8 hour tasks that were split over Friday to Monday. I ended up managing it manually with lag time but an auto option would be nice.

0
 
LVL 13

Accepted Solution

by:
jbfraser earned 450 total points
ID: 24116413
To keep a task from splitting you should use the "Elapsed" durations, ehrs, edays. When you enter the duration, just type 6eh for 6 elapsed hours. Then the duration will ignore non-working time.

But, this doesn't help with dynamically changing the lag. You could write a macro to do this without too much grief, but I don't think it would get used that much.
Some problems:
1. The default calendar has noon to one PM set as non-working time. So your 6 hour task would never be completed: It would get pushed out forever.
2. If this setting existed, what if you set your task to 10 hours, then what should happen? (Similar to number 1.)

Ths basic idea in the macro would be to look at every task in the project: if a certain custom field was set and if the task started after (5PM minus the task duration), then move the start to the next day.


James Fraser
0
 

Author Comment

by:nbozzy
ID: 24124254
jbfraser: good point about the lunch causing a 6-hour task to never get scheduled .... and thanks for the idea of the elapsed duration; that will help a good bit. And now I guess we're all sure that there is no existing way to force Project software to schedule a task to begin the next morning if it can't be completed on its calculated start date (can't be interrupted once it starts). Using the elapsed duration at least causes work to be scheduled through lunch and past the day's end time, so that's something. Thanks, jbfraser and dbase118!
0

Featured Post

Revamp Your Training Process

Drastically shorten your training time with WalkMe's advanced online training solution that Guides your trainees to action.

Question has a verified solution.

If you are experiencing a similar issue, please ask a related question

Suggested Solutions

Title # Comments Views Activity
Scrum and dominant team members 4 275
project management tool 5 189
how to let jenkins recognize where maven is located 2 1,006
Project Operations Manual 2 101
Online collaboration is quickly becoming embedded in the workplace, and its benefits are tangible. See what the current landscape looks like and what the future holds for collaboration tools and the future of work.
"Disruption" is the most feared word for C-level executives these days. They agonize over their industry being disturbed by another player - most likely by startups.
How to Install VMware Tools in Red Hat Enterprise Linux 6.4 (RHEL 6.4) Step-by-Step Tutorial
Finding and deleting duplicate (picture) files can be a time consuming task. My wife and I, our three kids and their families all share one dilemma: Managing our pictures. Between desktops, laptops, phones, tablets, and cameras; over the last decadeā€¦

738 members asked questions and received personalized solutions in the past 7 days.

Join the community of 500,000 technology professionals and ask your questions.

Join & Ask a Question