SAMRT UPS 1000 battery Replcement Date

Hi, I have just replace the battery in our SMART UPS 1000. I have gone into both the Powerchute Business Edition web interface and the Delux version software and CANNOT change the Battery Replacement Date. After I have alterered the date, it just resets itself to JAN 1980. I am changing the date with the UPS on and loaded. Does it have to be 0 load before I can change the date or is there something else going on here?
0
cwingrove
Asked:
cwingrove
  • 2
1 Solution
 
ComputerTechieCommented:
i belive you need to use the  APC Charge-UPS Refresher Kit.

CT
0
 
cwingroveAuthor Commented:
Is this a free download or something from APC?
0
 
ComputerTechieCommented:
it is software refresh the battery and align the ups with the batteris.

it came with my battery when i order them from apc.

CT
0

Featured Post

[Webinar] Cloud and Mobile-First Strategy

Maybe you’ve fully adopted the cloud since the beginning. Or maybe you started with on-prem resources but are pursuing a “cloud and mobile first” strategy. Getting to that end state has its challenges. Discover how to build out a 100% cloud and mobile IT strategy in this webinar.

  • 2
Tackle projects and never again get stuck behind a technical roadblock.
Join Now