Cost Report in Project 2007

I have a basic question about cost reports in Project 2007.  I have a task titled Construction with 2 subtasks titled Rebar, and Concrete.  If I add a cost of $10 to Rebar, and $10 to concrete then Construction will add the two and total $20.  I then collapse construction so that concrete and rebar are no longer visible but Construction still displays $20.  Now I want to view a cashflow report under Cost Reports.  When I do this it will not display the $20 next to Construction.  It will display the total dollar amount for the job but I was wondering if  there is a way to force project to show the total dollar amount of the parent task in the cash flow report?
jstergakisAsked:
Who is Participating?
 
BembiConnect With a Mentor CEOCommented:
I see...

Yes indeed, whatever you do, the value for the summary is empty. If you select resources from the report definition the resource summary is shown.

0
 
BembiCEOCommented:
Which report do you mean, the graphical ones? There are several.
0
 
jstergakisAuthor Commented:
Sorry Bembi, no I meant when you go to Report --> Reports --> Costs --> Cash Flow which looks more like a spreadsheet.
0
 
jstergakisAuthor Commented:
thank you
0
Question has a verified solution.

Are you are experiencing a similar issue? Get a personalized answer when you ask a related question.

Have a better answer? Share it in a comment.

All Courses

From novice to tech pro — start learning today.