Cost Report in Project 2007

Posted on 2009-05-06
4
Medium Priority
?
314 Views
Last Modified: 2013-11-15
I have a basic question about cost reports in Project 2007.  I have a task titled Construction with 2 subtasks titled Rebar, and Concrete.  If I add a cost of $10 to Rebar, and $10 to concrete then Construction will add the two and total $20.  I then collapse construction so that concrete and rebar are no longer visible but Construction still displays $20.  Now I want to view a cashflow report under Cost Reports.  When I do this it will not display the $20 next to Construction.  It will display the total dollar amount for the job but I was wondering if  there is a way to force project to show the total dollar amount of the parent task in the cash flow report?
0
Comment
Question by:jstergakis
[X]
Welcome to Experts Exchange

Add your voice to the tech community where 5M+ people just like you are talking about what matters.

  • Help others & share knowledge
  • Earn cash & points
  • Learn & ask questions
  • 2
  • 2
4 Comments
 
LVL 35

Expert Comment

by:Bembi
ID: 24341523
Which report do you mean, the graphical ones? There are several.
0
 

Author Comment

by:jstergakis
ID: 24364566
Sorry Bembi, no I meant when you go to Report --> Reports --> Costs --> Cash Flow which looks more like a spreadsheet.
0
 
LVL 35

Accepted Solution

by:
Bembi earned 1500 total points
ID: 24364919
I see...

Yes indeed, whatever you do, the value for the summary is empty. If you select resources from the report definition the resource summary is shown.

0
 

Author Comment

by:jstergakis
ID: 24388504
thank you
0

Featured Post

Free Tool: Site Down Detector

Helpful to verify reports of your own downtime, or to double check a downed website you are trying to access.

One of a set of tools we are providing to everyone as a way of saying thank you for being a part of the community.

Question has a verified solution.

If you are experiencing a similar issue, please ask a related question

Re-planning is just as important as planning. MS Project files need to be updated regularly to reflect the current status of the project and to streamline the upcoming tasks. We have seen a lot of issues where project managers have not updated the p…
"Disruption" is the most feared word for C-level executives these days. They agonize over their industry being disturbed by another player - most likely by startups.
If you’ve ever visited a web page and noticed a cool font that you really liked the look of, but couldn’t figure out which font it was so that you could use it for your own work, then this video is for you! In this Micro Tutorial, you'll learn yo…
Have you created a query with information for a calendar? ... and then, abra-cadabra, the calendar is done?! I am going to show you how to make that happen. Visualize your data!  ... really see it To use the code to create a calendar from a q…

752 members asked questions and received personalized solutions in the past 7 days.

Join the community of 500,000 technology professionals and ask your questions.

Join & Ask a Question