How do you include weekends in MS Project?

How do you get Project to recognize weekends as you do your planning??
LVL 2
amigan_99Network EngineerAsked:
Who is Participating?
I wear a lot of hats...

"The solutions and answers provided on Experts Exchange have been extremely helpful to me over the last few years. I wear a lot of hats - Developer, Database Administrator, Help Desk, etc., so I know a lot of things but not a lot about one thing. Experts Exchange gives me answers from people who do know a lot about one thing, in a easy to use platform." -Todd S.

dbase118Commented:
If you want Project to recognize weekends for all tasks then you will need to modify the standard calendar.  Go to Tools menu to Change Working Time. Make sure the calendar you are viewing is the standard calendar. In the calendar click on the S for Saturday and add in the normal work hours. Do the same for Sunday.

If you are only wanting certain tasks to be on a 7 day schedule then a different method would be used.

Hope this helps.
0

Experts Exchange Solution brought to you by

Your issues matter to us.

Facing a tech roadblock? Get the help and guidance you need from experienced professionals who care. Ask your question anytime, anywhere, with no hassle.

Start your 7-day free trial
amigan_99Network EngineerAuthor Commented:
Thank-you much.
0
It's more than this solution.Get answers and train to solve all your tech problems - anytime, anywhere.Try it for free Edge Out The Competitionfor your dream job with proven skills and certifications.Get started today Stand Outas the employee with proven skills.Start learning today for free Move Your Career Forwardwith certification training in the latest technologies.Start your trial today