How do I prevent task end date pushing out when dependent task resource allocation (%) is changed.

Avatar of cooperal31
cooperal31Flag for Australia asked on
Project ManagementProject Management Software
6 Comments1 Solution564 ViewsLast Modified:
We are experiencing an interesting issue where by when we decrease a resource allocation on a task to 40% or below, a subsequent tasks end date is pushed out. Attached is a before and after shot of the screen.

In the before shot you will see that task number 72 has the resource allocated at 41%. In the after shot, the resource is allocated at 40%. Notice that at 40%, task 74's end date is pushed out. However the duration does not change, nor does the work effort.

Even putting a constrain on the end date does not fix the issue.

I am open to any suggestions on this one as it has me baffled.

Cheers,

Andrew.
before.png
after.png
ASKER CERTIFIED SOLUTION
defi0

Our community of experts have been thoroughly vetted for their expertise and industry experience.

Join our community to see this answer!
Unlock 1 Answer and 6 Comments.
Start Free Trial
Learn from the best

Network and collaborate with thousands of CTOs, CISOs, and IT Pros rooting for you and your success.

Andrew Hancock - VMware vExpert
See if this solution works for you by signing up for a 7 day free trial.
Unlock 1 Answer and 6 Comments.
Try for 7 days

”The time we save is the biggest benefit of E-E to our team. What could take multiple guys 2 hours or more each to find is accessed in around 15 minutes on Experts Exchange.

-Mike Kapnisakis, Warner Bros