Microsoft Project Task Start Date

I have Tasks that won't let me change their start date no matter what i do.  Any ideas?
LVL 3
beaconlightboyAsked:
Who is Participating?
I wear a lot of hats...

"The solutions and answers provided on Experts Exchange have been extremely helpful to me over the last few years. I wear a lot of hats - Developer, Database Administrator, Help Desk, etc., so I know a lot of things but not a lot about one thing. Experts Exchange gives me answers from people who do know a lot about one thing, in a easy to use platform." -Todd S.

Ingeborg Hawighorst (Microsoft MVP / EE MVE)Microsoft MVP ExcelCommented:
Hello beaconlightboy,

check the tasks for

- fixed duration
- fixed end date
- dependency on predecessors

Anything there?

cheers, teylyn
0
Dr. Thomas HenkelmannDirector Consulting ServicesCommented:
Hi,

how are you changing the dates? Typing a new date in the start or finish field may fail if:
- the task has a constraint: double click the task, select the "Advanced" tab and make sure that the "Constraint Type" is set to "As soon as possible"
- the task has a predecessor: select the "Predecessor" tab and check if there are any tasks shown. If you NEED these predessors for the logical sequence of the tasks, keep them. However the latest finish of ALL predecessors will drive the task's start date

Regards

Thomas
0
beaconlightboyAuthor Commented:
I have tried to change the date a couple ways.
1. Double clicking the task in the gnatt view and changing the constraint type to start no earlier than x date and then setting the date.  This works for some but not all.  I have tried setting the constraint type to as soon as possible and this doesn't let me do it.

None of the tasks have predeccessors at this point.  when viewing the gnatt view the option to change the date is greyed out on the row item.  but only on some tasks.  A majority of the issues, but not all, are with the root tasks.
0
The Ultimate Tool Kit for Technolgy Solution Provi

Broken down into practical pointers and step-by-step instructions, the IT Service Excellence Tool Kit delivers expert advice for technology solution providers. Get your free copy for valuable how-to assets including sample agreements, checklists, flowcharts, and more!

Ingeborg Hawighorst (Microsoft MVP / EE MVE)Microsoft MVP ExcelCommented:
Hard to tell without seeing what you have in place. Can you post a sample file? Reduce to a few rows of data/tasks, just sufficient to illustrate the issue.
0
beaconlightboyAuthor Commented:
I have attahced a word doc with a screen shot.  Notice line 2.  PHASE 1.  i cannot change the start date from 8/10/2009.  Nor can i change the start date on the two tasks below which i have completed.  I just want to change the date for proper timeline display.  The other 3 cycles i can change the dates on.  But if you go to inventory and tag equipment, i cannot change that start date, but the dates underneath i can.  i don't get it.
error-example.doc
0
Ingeborg Hawighorst (Microsoft MVP / EE MVE)Microsoft MVP ExcelCommented:
A Word doc with a screen shot does nothing to help find out how your tasks and dependencies are set up.
0
Ingeborg Hawighorst (Microsoft MVP / EE MVE)Microsoft MVP ExcelCommented:
Line 2 is not a task, it's a summary row for a set of tasks.

The start date and duration of that row are calculated from the items that are defined nested inside that summary.

I feel you need a good look at the MS Project tutorial files to learn how to use MS Project and understand the  basic concepts of setting up a project.
0
beaconlightboyAuthor Commented:
Of this i am sure teylyn.
0
beaconlightboyAuthor Commented:
I found the error.  One of the child tasks way down was set to a bad date.   sigh..
0
ee_autoCommented:
Question PAQ'd, 500 points refunded, and stored in the solution database.
0

Experts Exchange Solution brought to you by

Your issues matter to us.

Facing a tech roadblock? Get the help and guidance you need from experienced professionals who care. Ask your question anytime, anywhere, with no hassle.

Start your 7-day free trial
It's more than this solution.Get answers and train to solve all your tech problems - anytime, anywhere.Try it for free Edge Out The Competitionfor your dream job with proven skills and certifications.Get started today Stand Outas the employee with proven skills.Start learning today for free Move Your Career Forwardwith certification training in the latest technologies.Start your trial today
Project Management Software

From novice to tech pro — start learning today.