multiple project question


Quick questions on Microsoft Project: I have several projects to track, can I specify each project as a task (or is Microsoft Project can only be used to track one project?)? When a person is in multiple project, it will have this warning in resource sheet:"This resource should be leveled based on a day to day setting". What is this message? So I assume in this case, a person can not be scheduled for two projects on the same day? How to resolve this if a person needs to work on multiple projects at the same time?
heyday2004Asked:
Who is Participating?
 
lyonstConnect With a Mentor Commented:
There are some good tutorials here that should help you:

http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23

In particular..

Microsoft Project: 18 – Multiple Project Management

http://pubs.logicalexpressions.com/Pub0009/LPMArticle.asp?ID=462

Microsoft Project: 20 – Levelling Multiple Projects

http://pubs.logicalexpressions.com/Pub0009/LPMArticle.asp?ID=500
0
 
lyonstCommented:
TY
0
All Courses