Push calendar change to the project

Posted on 2010-08-17
6
356 Views
Last Modified: 2013-11-15
I have access to PWA running Project Server 2007. On my comp. I have a trial of Project Professional 2007.

I've created a project in PWA from a 2007 project file, when doing so it changed my finish dates. Likely due to the fact that the original enterprise calendar has Sat & Sun's off. I made the adjustment to that enterprise calendar now how do I update my finish dates in the project?
0
Comment
Question by:rsirinek6849
[X]
Welcome to Experts Exchange

Add your voice to the tech community where 5M+ people just like you are talking about what matters.

  • Help others & share knowledge
  • Earn cash & points
  • Learn & ask questions
  • 3
  • 2
6 Comments
 
LVL 10

Expert Comment

by:SANTABABY
ID: 33457616
Please try to level resource after you've made changes to the calendar. The option is available under the tools menu.
0
 

Author Comment

by:rsirinek6849
ID: 33458131
Didn't seem to edit the . I have no resources in my project.... not my design. They plan via duration and predecessors. Is that the problem?
0
 

Author Comment

by:rsirinek6849
ID: 33458449
what i did to fix it was to set the first task to the calendar i wanted all the tasks to use. Now my PWA project has the same dates at the local.
0
Salesforce Made Easy to Use

On-screen guidance at the moment of need enables you & your employees to focus on the core, you can now boost your adoption rates swiftly and simply with one easy tool.

 
LVL 10

Expert Comment

by:SANTABABY
ID: 33458673
The tasks which have no resource are treated as they are done by the unassigned (predefined in project) resource.
Anyway, I created a similar scenario like yours in Project 2003. The completion dates DO change as I change working time in my project calendar.
I recommend you to double check your calendar (Tools->Change working time ) and make sure that non-working days are marked properly.
If you want, you may post a sample project file (.mpp) here.
Thanks.
0
 
LVL 12

Accepted Solution

by:
Dr. Thomas Henkelmann earned 250 total points
ID: 33462661
Hi,

to make calendar changes available to all projects you need to go to "Server Settings".."Enterprise Calendar". Select a calendar (usually "Standard") and edit as needed.

Then open the project from the server and check/set in "Project"..Project Information" that this calendar is selected. This makes sure that all tasks in the project use this calendar as well.

Regards

Thomas
0
 

Author Closing Comment

by:rsirinek6849
ID: 33681739
no
0

Featured Post

PeopleSoft Has Never Been Easier

PeopleSoft Adoption Made Smooth & Simple!

On-The-Job Training Is made Intuitive & Easy With WalkMe's On-Screen Guidance Tool.  Claim Your Free WalkMe Account Now

Question has a verified solution.

If you are experiencing a similar issue, please ask a related question

Learn how ViaSat reduced average response times for IT incidents from 10 minutes to 30 seconds.
A simple overview of the possibilities of using technology for project management.
If you're a developer or IT admin, you’re probably tasked with managing multiple websites, servers, applications, and levels of security on a daily basis. While this can be extremely time consuming, it can also be frustrating when systems aren't wor…
Add bar graphs to Access queries using Unicode block characters. Graphs appear on every record in the color you want. Give life to numbers. Hopes this gives you ideas on visualizing your data in new ways ~ Create a calculated field in a query: …

707 members asked questions and received personalized solutions in the past 7 days.

Join the community of 500,000 technology professionals and ask your questions.

Join & Ask a Question