Solved

How to set the project only work week day in MS Project

Posted on 2010-08-25
3
602 Views
Last Modified: 2013-11-15
When I first create the project I count every day as working day. Now I try to make a more realistic schedule since I know the start date now.  

How to I do in MS Project 2003?
0
Comment
Question by:tommym121
3 Comments
 
LVL 30

Accepted Solution

by:
Brad Howe earned 250 total points
ID: 33527561
Hi,
MS Project is a full time jb and does take some time to figure out. To start, I would suggest reading this Microsoft article. It explais the 4 types of calanders in Project.
http://office.microsoft.com/en-us/project-help/setting-working-times-and-days-off-by-using-project-calendars-HA001020995.aspx
If you have questions after this, let me know and I'd be glad to help.
Hades666
0
 
LVL 2

Assisted Solution

by:Pagefright
Pagefright earned 250 total points
ID: 33527846
I litrally just got done looking into this for myself and would recommend the following videos and sites,

http://www.youtube.com/watch?v=opjNsVnMNpg
http://www.youtube.com/watch?v=OTPayf61vFE
*load these up in 480p instead of 360

http://search.techrepublic.com.com/index.php?q=Microsoft+Project+tutorial&t=11&go=Search

Good luck, your life will be better with MS Projects in it :)
0
 

Author Closing Comment

by:tommym121
ID: 33535131
Not quite, but thanks for the input.
I need to remove the constrain in Task Info.
0

Featured Post

Courses: Start Training Online With Pros, Today

Brush up on the basics or master the advanced techniques required to earn essential industry certifications, with Courses. Enroll in a course and start learning today. Training topics range from Android App Dev to the Xen Virtualization Platform.

Question has a verified solution.

If you are experiencing a similar issue, please ask a related question

Suggested Solutions

Title # Comments Views Activity
Project plan 6 486
PMP Certification 3 99
Scrum:  Assignement of Product Owners and Scrum Masters 3 161
MSP macro not working in project server 4 121
Re-planning is just as important as planning. MS Project files need to be updated regularly to reflect the current status of the project and to streamline the upcoming tasks. We have seen a lot of issues where project managers have not updated the p…
A simple overview of the possibilities of using technology for project management.
Windows 10 is mostly good. However the one thing that annoys me is how many clicks you have to do to dial a VPN connection. You have to go to settings from the start menu, (2 clicks), Network and Internet (1 click), Click VPN (another click) then fi…
Sending a Secure fax is easy with eFax Corporate (http://www.enterprise.efax.com). First, just open a new email message. In the To field, type your recipient's fax number @efaxsend.com. You can even send a secure international fax — just include t…

815 members asked questions and received personalized solutions in the past 7 days.

Join the community of 500,000 technology professionals and ask your questions.

Join & Ask a Question

Need Help in Real-Time?

Connect with top rated Experts

13 Experts available now in Live!

Get 1:1 Help Now