How to set the project only work week day in MS Project

Posted on 2010-08-25
3
Medium Priority
?
636 Views
Last Modified: 2013-11-15
When I first create the project I count every day as working day. Now I try to make a more realistic schedule since I know the start date now.  

How to I do in MS Project 2003?
0
Comment
Question by:tommym121
3 Comments
 
LVL 30

Accepted Solution

by:
Brad Howe earned 750 total points
ID: 33527561
Hi,
MS Project is a full time jb and does take some time to figure out. To start, I would suggest reading this Microsoft article. It explais the 4 types of calanders in Project.
http://office.microsoft.com/en-us/project-help/setting-working-times-and-days-off-by-using-project-calendars-HA001020995.aspx
If you have questions after this, let me know and I'd be glad to help.
Hades666
0
 
LVL 2

Assisted Solution

by:Pagefright
Pagefright earned 750 total points
ID: 33527846
I litrally just got done looking into this for myself and would recommend the following videos and sites,

http://www.youtube.com/watch?v=opjNsVnMNpg
http://www.youtube.com/watch?v=OTPayf61vFE
*load these up in 480p instead of 360

http://search.techrepublic.com.com/index.php?q=Microsoft+Project+tutorial&t=11&go=Search

Good luck, your life will be better with MS Projects in it :)
0
 

Author Closing Comment

by:tommym121
ID: 33535131
Not quite, but thanks for the input.
I need to remove the constrain in Task Info.
0

Featured Post

Free Tool: ZipGrep

ZipGrep is a utility that can list and search zip (.war, .ear, .jar, etc) archives for text patterns, without the need to extract the archive's contents.

One of a set of tools we're offering as a way to say thank you for being a part of the community.

Question has a verified solution.

Are you are experiencing a similar issue? Get a personalized answer when you ask a related question.

Have a better answer? Share it in a comment.

Join & Write a Comment

Re-planning is just as important as planning. MS Project files need to be updated regularly to reflect the current status of the project and to streamline the upcoming tasks. We have seen a lot of issues where project managers have not updated the p…
A simple overview of the possibilities of using technology for project management.
Hi, this video explains a free download that you can incorporate into your Access databases, or use stand-alone for contact management. Contacts -- Names, Addresses, Phone Numbers, eMail Addresses, Websites, Lists, Projects, Notes, Attachments…
Through the video, you can check the migration process of Outlook PST file to PDF. Kernel for Outlook to PDF tool can convert Outlook emails with all attributes like Subject, To, From, Cc, Bcc and other folders such as Inbox, Outbox, Sent Items, Jun…

569 members asked questions and received personalized solutions in the past 7 days.

Join the community of 500,000 technology professionals and ask your questions.

Join & Ask a Question