When I first create the project I count every day as working day. Now I try to make a more realistic schedule since I know the start date now.  

How to I do in MS Project 2003?
0
Comment
Question by:tommym121
3 Comments
 
LVL 30

Accepted Solution

by:
Brad Howe earned 250 total points
ID: 33527561
Hi,
MS Project is a full time jb and does take some time to figure out. To start, I would suggest reading this Microsoft article. It explais the 4 types of calanders in Project.
http://office.microsoft.com/en-us/project-help/setting-working-times-and-days-off-by-using-project-calendars-HA001020995.aspx
If you have questions after this, let me know and I'd be glad to help.
Hades666
0
 
LVL 2

Assisted Solution

by:Pagefright
Pagefright earned 250 total points
ID: 33527846
I litrally just got done looking into this for myself and would recommend the following videos and sites,

http://www.youtube.com/watch?v=opjNsVnMNpg
http://www.youtube.com/watch?v=OTPayf61vFE
*load these up in 480p instead of 360

http://search.techrepublic.com.com/index.php?q=Microsoft+Project+tutorial&t=11&go=Search

Good luck, your life will be better with MS Projects in it :)
0
 

Author Closing Comment

by:tommym121
ID: 33535131
Not quite, but thanks for the input.
I need to remove the constrain in Task Info.
0

Featured Post

Is Your Active Directory as Secure as You Think?

More than 75% of all records are compromised because of the loss or theft of a privileged credential. Experts have been exploring Active Directory infrastructure to identify key threats and establish best practices for keeping data safe. Attend this month’s webinar to learn more.

Question has a verified solution.

If you are experiencing a similar issue, please ask a related question

Suggested Solutions

Title # Comments Views Activity
Comments in MS Project 2013? 2 436
Collaborative web site/tool/technique for building our new house 2 220
MS Project 2013 - actual finish date 1 213
Software quality certificate 3 81
Article by: x-men
Where used to see Gantt charts for illustrating project timelines, but what if I wanted to visualize passed timed events? Here's how.
When we talk about DevOps toolchains, I sometimes wonder how many people really get what we’re talking about. I don’t know if it’s just semantics or tone or something else, but sometimes I think it just sounds like buzzword sausage. So it’s always …
This Micro Tutorial demonstrates using Microsoft Excel pivot tables, how to reverse engineer competitors' marketing strategies through backlinks.
Windows 10 is mostly good. However the one thing that annoys me is how many clicks you have to do to dial a VPN connection. You have to go to settings from the start menu, (2 clicks), Network and Internet (1 click), Click VPN (another click) then fi…

920 members asked questions and received personalized solutions in the past 7 days.

Join the community of 500,000 technology professionals and ask your questions.

Join & Ask a Question

Need Help in Real-Time?

Connect with top rated Experts

14 Experts available now in Live!

Get 1:1 Help Now