Move Project Server 2007 Databases to Different Server

I have a project server 2007 installation using a separate SQL005 database server. I want to move the databases to a new SQL2008R2 server but i am stuggling to find some simple instructions for this. The databases I need to move are:

ProjectServer_Archive
ProjectServer_Draft
ProjectServer_Published
ProjectServer_Reporting
Proj_SSP
PWA_Content
PWA_SSP_Content
SharePoint_AdminContent
SharePoint_Config
WSS_Search_AWPROJECT
0
allan_jardine
Asked:
allan_jardine
  • 2
1 Solution
 
allan_jardineAuthor Commented:
Hi Bembi - thanks for the response but the article refers to moving from one environment to another and all i want to do is move the databases to a new server. I have achieved this in the end by setting a server alias using the SQL Client Network Utility CLICONFG
0
 
allan_jardineAuthor Commented:
this was the simplest method of moving the databases to a new server
0
Question has a verified solution.

Are you are experiencing a similar issue? Get a personalized answer when you ask a related question.

Have a better answer? Share it in a comment.

Join & Write a Comment

Featured Post

Get your problem seen by more experts

Be seen. Boost your question’s priority for more expert views and faster solutions

  • 2
Tackle projects and never again get stuck behind a technical roadblock.
Join Now