I have created a project plan in MS Project 2007.

In the Resource Sheet view I can see 2 unwanted resources which were entered by mistake (they were added because resource name was incorrectly typed in Gantt Chart view). In this state all remaining resources are correctly allocated and these 2 resources are not at all allocated anywhere.
Now when I remove these resources from the Resource Sheet, all other resources become overallocated.
I am not able to make out why this is happening.
Can someone please help me with it.
Thank you
0
Comment
Question by:ank5
[X]
Welcome to Experts Exchange

Add your voice to the tech community where 5M+ people just like you are talking about what matters.

  • Help others & share knowledge
  • Earn cash & points
  • Learn & ask questions
  • 2
2 Comments
 
LVL 15

Accepted Solution

by:
dbase118 earned 2000 total points
ID: 34871346
ank5,

Again I would start by checking the Resource Usage View and make sure that the resource has 0 total hours contributed toward the project. If you see  hours allocated to that resource, you should be able to find out which days and tasks those hours are coming from and go back and review them.

It is also possible that the tasks got put in as fixed duration. So you had 2 resources doing a task for 1 week. If you remove one resource instead of saying it would now take 2 weeks (Half resources-Double the time) it might have kept the duration of 1 week and doubled the hours worked by the remaining resource causing the over allocation.

Third option there is a Resource Management toolbar that you can get to by right clicking your toolbars and selecting it. On this toolbar there is a find next overallocation button that will allow you to search for places where the resources are over-allocated and try to fix them that way.
0
 
LVL 15

Expert Comment

by:dbase118
ID: 34887872
Did you find the problem?
0

Featured Post

Hire Technology Freelancers with Gigs

Work with freelancers specializing in everything from database administration to programming, who have proven themselves as experts in their field. Hire the best, collaborate easily, pay securely, and get projects done right.

Question has a verified solution.

If you are experiencing a similar issue, please ask a related question

At the office, we’ve started to get serious about organizing what we’re doing. I mean, it was getting to the point where every time I received a phone call, it began with “I know you’re really busy, but…” My boss was taking tasks away from me left a…
Re-planning is just as important as planning. MS Project files need to be updated regularly to reflect the current status of the project and to streamline the upcoming tasks. We have seen a lot of issues where project managers have not updated the p…
Video by: ITPro.TV
In this episode Don builds upon the troubleshooting techniques by demonstrating how to properly monitor a vSphere deployment to detect problems before they occur. He begins the show using tools found within the vSphere suite as ends the show demonst…
In this video, Percona Solutions Engineer Barrett Chambers discusses some of the basic syntax differences between MySQL and MongoDB. To learn more check out our webinar on MongoDB administration for MySQL DBA: https://www.percona.com/resources/we…

610 members asked questions and received personalized solutions in the past 7 days.

Join the community of 500,000 technology professionals and ask your questions.

Join & Ask a Question