Overallocation of a resource

Posted on 2011-02-12
3
500 Views
Last Modified: 2013-11-15
If I go to the Resource Usage view, I can see that a resource is allocated 8 hours on a certain day. But still it is highlighted in RED which means that the resource is over-allocated on that day.

Please let me know how this could be possible.

thank you

0
Comment
Question by:ank5
3 Comments
 
LVL 1

Author Comment

by:ank5
ID: 34881650
0
 
LVL 12

Accepted Solution

by:
thausla earned 250 total points
ID: 34882886
Is the task duration less than the standard 8h on this Monday? This could cause the resource allocation to be higher than 100%, e.g. if the resource needs to deliver work 8h in a 4h task. Can you please check the start and finish dates and show the times of all tasks that lead to the 8h total on this day?
0
 
LVL 18

Assisted Solution

by:Richard Daneke
Richard Daneke earned 250 total points
ID: 34916507
The resource could not be working on the Fourth of July - and therefore is overallocated 8 hours on a day off!
Over allocation considers the project calendar, specific task calendar(if any), and individual resource calendar(if any) in determing overallocation.
0

Featured Post

Gigs: Get Your Project Delivered by an Expert

Select from freelancers specializing in everything from database administration to programming, who have proven themselves as experts in their field. Hire the best, collaborate easily, pay securely and get projects done right.

Question has a verified solution.

If you are experiencing a similar issue, please ask a related question

Suggested Solutions

Title # Comments Views Activity
IT Desktop Support 11 65
Office 365 home questions 7 65
MS Project 2013 standar edition will not active key in one computer. 5 20
Install both Office 2010 and 2013 4 35
Recently Microsoft released a brand new function called CONCAT. It's supposed to replace its predecessor CONCATENATE. But how does it work? And what's new? In this article, we take a closer look at all of this - we even included an exercise file for…
A simple overview of the possibilities of using technology for project management.
The view will learn how to download and install SIMTOOLS and FORMLIST into Excel, how to use SIMTOOLS to generate a Monte Carlo simulation of 30 sales calls, and how to calculate the conditional probability based on the results of the Monte Carlo …
The viewer will learn how to use a discrete random variable to simulate the return on an investment over a period of years, create a Monte Carlo simulation using the discrete random variable, and create a graph to represent the possible returns over…

786 members asked questions and received personalized solutions in the past 7 days.

Join the community of 500,000 technology professionals and ask your questions.

Join & Ask a Question