Overallocation of a resource

If I go to the Resource Usage view, I can see that a resource is allocated 8 hours on a certain day. But still it is highlighted in RED which means that the resource is over-allocated on that day.

Please let me know how this could be possible.

thank you

Who is Participating?
Dr. Thomas HenkelmannConnect With a Mentor Director Consulting ServicesCommented:
Is the task duration less than the standard 8h on this Monday? This could cause the resource allocation to be higher than 100%, e.g. if the resource needs to deliver work 8h in a 4h task. Can you please check the start and finish dates and show the times of all tasks that lead to the 8h total on this day?
ank5Author Commented:
Richard DanekeConnect With a Mentor TrainerCommented:
The resource could not be working on the Fourth of July - and therefore is overallocated 8 hours on a day off!
Over allocation considers the project calendar, specific task calendar(if any), and individual resource calendar(if any) in determing overallocation.
Question has a verified solution.