Hello Experts!
i have a problem with a project manager, he is the only one not able to import timesheets in "my tasks" page. he finds only his project tasks and not others tasks assigned by other PM.
i checked his credentials using also a project server resource kits tool, all seems ok.
i published a new project with new tasks assigned to him, he see them in the timesheet but when he go to My tasks page > import timesheet > the new tasks are not listed here @-@
i tried his credentials and PWA access using a different pc, no changes.
have you any idea what could be the problem? suggestions? THANKS. Andrea.-
0
Comment
Question by:ITDataCenter
[X]
Welcome to Experts Exchange

Add your voice to the tech community where 5M+ people just like you are talking about what matters.

  • Help others & share knowledge
  • Earn cash & points
  • Learn & ask questions
  • 2
3 Comments
 
LVL 10

Expert Comment

by:Minesh Shah
ID: 35034025
should be a permission issue. verify his perissions and compare with the one of whom this works perfectly.
keep posting
0
 
LVL 1

Accepted Solution

by:
ITDataCenter earned 0 total points
ID: 35111104
problem solved, this project manager was previously a project resource only. the other project managers set up on their projects a different "Assignment Owner" of the tasks where he was "Resource Name"

I asked to the project manager to update all tasks where this guy was set as resource, in order to have his name on "resource name" and "assignment owner"

after this change, the tasks appeared on this timesheets and my tasks panel :D

0
 
LVL 1

Author Closing Comment

by:ITDataCenter
ID: 35145546
no comment
0

Featured Post

Industry Leaders: We Want Your Opinion!

We value your feedback.

Take our survey and automatically be enter to win anyone of the following:
Yeti Cooler, Amazon eGift Card, and Movie eGift Card!

Question has a verified solution.

If you are experiencing a similar issue, please ask a related question

These days socially coordinated efforts have turned into a critical requirement for enterprises.
A recent project that involved parsing Tableau Desktop and Server log files to extract reusable user queries for use in other systems. I chose to use PowerShell to gather the data, and SharePoint to present it...
Simple Linear Regression
Progress

662 members asked questions and received personalized solutions in the past 7 days.

Join the community of 500,000 technology professionals and ask your questions.

Join & Ask a Question