Consolidate Excel values into  final aggregated groups

Posted on 2011-02-21
10
248 Views
Last Modified: 2012-05-11
I have an Excel sheet . It consists of the projects expenditures of each project for different months. Some projects would have more than one entry. The expenditures are in billions of dollars.

Some projects would start in Jan and would end by Dec. So that Start quarter would be Q1 and end quarter would be Q4. Some projects would start in Apr and the end by Dec. So the start quarter for them is Q2 and End quarter is Q4.
If a project is started in a certain quarter, then atleast one cell value in that quarter would have an expenditure value. If  all the project entry values for all the months are 0.00 then it means that the project had ended in that value.
For example if a project had 4 entries and all the values of that project from Oct to December are 0.00 it means the project ended by Sept. The project end quarter is Q3.
Similarily, if the project had 4 entries and all values of that project from Jan to March are 0.00 then the project had no entries in Q1  and the project start quarter is Q2.

I am attaching the input Excel sheet and the out put that I am expecting
Could some one please suggest a VBA code as to how to achieve it?

Thanks

PROJ-SALES.xls
0
Comment
Question by:vsuripeddi
  • 6
  • 3
10 Comments
 

Author Comment

by:vsuripeddi
ID: 34945715
Please submit Excel VBA code
0
 
LVL 45

Expert Comment

by:patrickab
ID: 34945882
vsuripeddi,

In cell D26 you could use this formula and copy it down the column:

=SUMPRODUCT(AND(MONTH($B$1:$M$1)>=B26,MONTH($B$1:$M$1)<=C26)*($A$2:$A$18=A26)*$B$2:$M$18)

It's in the attached file.

Patrick
PROJ-SALES-01.xls
0
 
LVL 45

Expert Comment

by:patrickab
ID: 34946049
vsuripeddi,

Perhaps the attached file is better. Please check it out.

Patrick
PROJ-SALES-02.xls
0
Networking for the Cloud Era

Join Microsoft and Riverbed for a discussion and demonstration of enhancements to SteelConnect:
-One-click orchestration and cloud connectivity in Azure environments
-Tight integration of SD-WAN and WAN optimization capabilities
-Scalability and resiliency equal to a data center

 
LVL 1

Accepted Solution

by:
dev00790 earned 500 total points
ID: 34946119
vsuripeddi - All done using simple excel formulae.

Patrick - My numbers are different to yours. Please review. Eg - Is Project D supposed to have 0 cost?

File is attached. I have calculated cost of each project each month using sumif()'s, then have totaled them for output.

 PROJ-SALES-NP.xls
0
 
LVL 1

Expert Comment

by:dev00790
ID: 34946139
Ok I understand now. Let me work through it.
0
 
LVL 45

Expert Comment

by:patrickab
ID: 34946296
vsuripeddi,

Apologies there were errors in my formulae. It's now all done with simple formulae in the attached file.

eg:

=SUMPRODUCT((MONTH($B$1:$M$1)>=B26)*(MONTH($B$1:$M$1)<=C26)*($A$2:$A$18=A26)*$B$2:$M$18)

Patrick
PROJ-SALES-03.xls
0
 
LVL 1

Expert Comment

by:dev00790
ID: 34946781
Atttached is my spreadhsheet earlier, but now included VBA macro to fill in Quarters for you.
Just press the grey button in file.

Hope that one of the two helps!

dev00790. PROJ-SALES-NP.xls
0
 
LVL 45

Expert Comment

by:patrickab
ID: 34946818
vsuripeddi,

Perhaps one of the advantages of using SUMPRODUCT() is that no VBA is needed and it is quick to set up.

Patrick
0
 
LVL 45

Expert Comment

by:patrickab
ID: 34946909
vsuripeddi,

I have changed the formulae in the attached file so that you can still specify Quarters for the start and finish and the formula can translate those into start and finish months. It's in the attached file. The formula now has the format as follows:

=SUMPRODUCT((MONTH($B$1:$M$1)>=HLOOKUP(B26,{"Q1","Q2","Q3","Q4";1,4,7,12},2,0))*(MONTH($B$1:$M$1)<=HLOOKUP(C26,{"Q1","Q2","Q3","Q4";1,4,7,12},2,0))*($A$2:$A$18=A26)*$B$2:$M$18)

It looks complicated but in fact it isn't really. It's great advantage is that no VBA is needed and no changes are needed to the data on the worksheet.

Patrick
PROJ-SALES-04.xls
0
 
LVL 45

Expert Comment

by:patrickab
ID: 34962419
vsuripeddi,

Did you have time to look at my formula only solution in comment ID:34946909?

Patrick
0

Featured Post

Free Tool: Site Down Detector

Helpful to verify reports of your own downtime, or to double check a downed website you are trying to access.

One of a set of tools we are providing to everyone as a way of saying thank you for being a part of the community.

Question has a verified solution.

If you are experiencing a similar issue, please ask a related question

Approximate matching with VLOOKUP and MATCH seems to me to be a greatly under-used technique, and one which is vital for getting good performance out of large lookups. Until recently I would always have advised using an exact match for simplicity an…
Excel can be a tricky bit of software to get your head around. Whilst you’ll be able to eventually get to grips with the basic understanding of how to get by, there are a few Excel tips that not everybody will even know about let alone know how to d…
This Micro Tutorial will demonstrate in Google Sheets how to use the HYPERLINK function to create live links inside your spreadsheet.
Although Jacob Bernoulli (1654-1705) has been credited as the creator of "Binomial Distribution Table", Gottfried Leibniz (1646-1716) did his dissertation on the subject in 1666; Leibniz you may recall is the co-inventor of "Calculus" and beat Isaac…

856 members asked questions and received personalized solutions in the past 7 days.

Join the community of 500,000 technology professionals and ask your questions.

Join & Ask a Question