MS Project - access Project Summary Task in VBA?

Posted on 2011-03-17
4
1,927 Views
Last Modified: 2012-06-27
Is there a way to access the Project Summary Task in vba (when Show Project Summary Task is checked in Options | View)? When the mpp is exported to Excel, the Project Summary Task, with ID 0, is included, but when I traverse the tasks in VBA (For Each Task In
ActiveProject.Tasks) The Project Summary/TaskID 0 is not included, but if it has child tasks they are included. The resulting recordset doesn't make much sense.

I have an automation project that needs the Project Summary Task, if it is selected in the mpp. I suppose I could save the mpp to xls before working with the tasks in vba, but I'd rather avoid that step if possible.
0
Comment
Question by:dgmoore1
[X]
Welcome to Experts Exchange

Add your voice to the tech community where 5M+ people just like you are talking about what matters.

  • Help others & share knowledge
  • Earn cash & points
  • Learn & ask questions
  • 3
4 Comments
 
LVL 12

Expert Comment

by:Dr. Thomas Henkelmann
ID: 35171903
You can use the project summary task with ActiveProject.Tasks.UniqueID(0). This is independent from the settings in Options..View.
0
 

Author Comment

by:dgmoore1
ID: 35172011
Interesting. I wonder why it isn't returned when you iterate For All Tasks in ActiveProject.Tasks...  I'll try this in my code and see what I get
0
 

Accepted Solution

by:
dgmoore1 earned 0 total points
ID: 35461933
I have determined that in order for the procedure I have developed to work correctly, the project summary task must be in MSP_TASKS. I am instructing my users not to employ Project's Show Project Summary Task.
0
 

Author Closing Comment

by:dgmoore1
ID: 35496484
Determined that the project summary task, if used, must be in the Tasks table.
0

Featured Post

Online Training Solution

Drastically shorten your training time with WalkMe's advanced online training solution that Guides your trainees to action. Forget about retraining and skyrocket knowledge retention rates.

Question has a verified solution.

If you are experiencing a similar issue, please ask a related question

Re-planning is just as important as planning. MS Project files need to be updated regularly to reflect the current status of the project and to streamline the upcoming tasks. We have seen a lot of issues where project managers have not updated the p…
Learn how ViaSat reduced average response times for IT incidents from 10 minutes to 30 seconds.
Finds all prime numbers in a range requested and places them in a public primes() array. I've demostrated a template size of 30 (2 * 3 * 5) but larger templates can be built such 210  (2 * 3 * 5 * 7) or 2310  (2 * 3 * 5 * 7 * 11). The larger templa…
Exchange organizations may use the Journaling Agent of the Transport Service to archive messages going through Exchange. However, if the Transport Service is integrated with some email content management application (such as an antispam), the admini…

733 members asked questions and received personalized solutions in the past 7 days.

Join the community of 500,000 technology professionals and ask your questions.

Join & Ask a Question