Microsoft Project - Header Title needed

Posted on 2011-03-18
2
655 Views
Last Modified: 2013-11-15
I would like to create permananent (non-modifiable) Main Tasks in Project 2010 to serve as a title or placeholder for sub tasks.  I don't want them to have either a start of finish date (similar to the attached image).  They are merely fixed placeholders.

Example structure:

Sales Calls  << act as a header/title only
--Call John Doe  << normal task
--Call Jane Doe  <<normal task

Field Visits
--Visit John Doe
--Visit Jane Doe

I can work around this by blanking out the fields but the dates get filled in when the sub tasks are 100% completed.

I don't know if tasks are the method to best accomplish what I need so I'm open to other ideas.
Example.jpg
0
Comment
Question by:mcnuttlaw
[X]
Welcome to Experts Exchange

Add your voice to the tech community where 5M+ people just like you are talking about what matters.

  • Help others & share knowledge
  • Earn cash & points
  • Learn & ask questions
2 Comments
 
LVL 12

Accepted Solution

by:
Dr. Thomas Henkelmann earned 500 total points
ID: 35171948
Hi,

not sure I fully understand your question? Summary tasks in Microsoft Project always calculate their fields (start, finish, cost, work, custom fields) based on the detail tasks below. Also you screen shot shows Project 2007?
If your using Project 2010 you can set the Summary tasks to "Manual scheduled" (and optionally the details tasks to "Automatic Scheduled". This will prevent the summary tasks from calculating their dates or duration.

Hope this helps

Thomas
0
 
LVL 2

Author Comment

by:mcnuttlaw
ID: 35259174
I would prefer titles/headers as the image shows but this is a workaround to what I need..
0

Featured Post

Enroll in June's Course of the Month

June's Course of the Month is now available! Every 10 seconds, a consumer gets hit with ransomware. Refresh your knowledge of ransomware best practices by enrolling in this month's complimentary course for Premium Members, Team Accounts, and Qualified Experts.

Question has a verified solution.

If you are experiencing a similar issue, please ask a related question

Re-planning is just as important as planning. MS Project files need to be updated regularly to reflect the current status of the project and to streamline the upcoming tasks. We have seen a lot of issues where project managers have not updated the p…
A simple overview of the possibilities of using technology for project management.
There's a multitude of different network monitoring solutions out there, and you're probably wondering what makes NetCrunch so special. It's completely agentless, but does let you create an agent, if you desire. It offers powerful scalability …
Michael from AdRem Software explains how to view the most utilized and worst performing nodes in your network, by accessing the Top Charts view in NetCrunch network monitor (https://www.adremsoft.com/). Top Charts is a view in which you can set seve…

729 members asked questions and received personalized solutions in the past 7 days.

Join the community of 500,000 technology professionals and ask your questions.

Join & Ask a Question