Microsoft Project - Header Title needed

Posted on 2011-03-18
2
Medium Priority
?
661 Views
Last Modified: 2013-11-15
I would like to create permananent (non-modifiable) Main Tasks in Project 2010 to serve as a title or placeholder for sub tasks.  I don't want them to have either a start of finish date (similar to the attached image).  They are merely fixed placeholders.

Example structure:

Sales Calls  << act as a header/title only
--Call John Doe  << normal task
--Call Jane Doe  <<normal task

Field Visits
--Visit John Doe
--Visit Jane Doe

I can work around this by blanking out the fields but the dates get filled in when the sub tasks are 100% completed.

I don't know if tasks are the method to best accomplish what I need so I'm open to other ideas.
Example.jpg
0
Comment
Question by:mcnuttlaw
[X]
Welcome to Experts Exchange

Add your voice to the tech community where 5M+ people just like you are talking about what matters.

  • Help others & share knowledge
  • Earn cash & points
  • Learn & ask questions
2 Comments
 
LVL 12

Accepted Solution

by:
Dr. Thomas Henkelmann earned 2000 total points
ID: 35171948
Hi,

not sure I fully understand your question? Summary tasks in Microsoft Project always calculate their fields (start, finish, cost, work, custom fields) based on the detail tasks below. Also you screen shot shows Project 2007?
If your using Project 2010 you can set the Summary tasks to "Manual scheduled" (and optionally the details tasks to "Automatic Scheduled". This will prevent the summary tasks from calculating their dates or duration.

Hope this helps

Thomas
0
 
LVL 2

Author Comment

by:mcnuttlaw
ID: 35259174
I would prefer titles/headers as the image shows but this is a workaround to what I need..
0

Featured Post

[Webinar] Lessons on Recovering from Petya

Skyport is working hard to help customers recover from recent attacks, like the Petya worm. This work has brought to light some important lessons. New malware attacks like this can take down your entire environment. Learn from others mistakes on how to prevent Petya like worms.

Question has a verified solution.

If you are experiencing a similar issue, please ask a related question

Article by: x-men
Where used to see Gantt charts for illustrating project timelines, but what if I wanted to visualize passed timed events? Here's how.
"Disruption" is the most feared word for C-level executives these days. They agonize over their industry being disturbed by another player - most likely by startups.
This is my first video review of Microsoft Bookings, I will be doing a part two with a bit more information, but wanted to get this out to you folks.
In this video, Percona Solution Engineer Dimitri Vanoverbeke discusses why you want to use at least three nodes in a database cluster. To discuss how Percona Consulting can help with your design and architecture needs for your database and infras…

704 members asked questions and received personalized solutions in the past 7 days.

Join the community of 500,000 technology professionals and ask your questions.

Join & Ask a Question