pmcoordinator
asked on
How to calculate BCWS and BCWP and CV based on the information saved in Baseline 1
I need to be able to compare various schedules in my project plan, one of which includes the BCWS and BCWP based on the Schedule I saved in baseline 1. And then, also to be able to see the variance based on Baseline 1 vs. Actual (aka CV in MS Project). Do I need to build a macro for this, since I haven't seen such an option in MS Project, and if the answer is yes, what would be the code that would apply in this case. MS Project only provides the BCWS and BCWP based on the baseline schedule not on baseline 1 schedule.
ASKER
Yes, that works. My question now is, what if I want to see the EVA caclulations based on baseline and baseline 1 all in one view at the same time, so I can compare the numbers. Is that possible, or I can only view that for one baseline at a time.
Thanks!
Thanks!
ASKER CERTIFIED SOLUTION
membership
This solution is only available to members.
To access this solution, you must be a member of Experts Exchange.
ASKER
the exact answer for this question was not provided.
this depends on the version of MSP you are using:
For the 2010 version you can select the baseline for EVA in the options at File..Options..Advanced..E
For 2007 you find the same in Tools..Options..Calculatio
Regards
Thomas