What is BCWP formula?

Need to know the exact formula for BCWP in MS Project.
Avatar of dbase118
dbase118
Flag of United States of America image

BCWP (Budgeted Cost of Worked Performed) is simply the calculated cost of the task based on the status date. It assumes that all work is done according to schedule.

So for a given task the BCWP formulas is Total Cost * % complete.  %completed is determined by  using  STATUS DATE - START DATE / FINISH DATE - START DATE)