Solved

Microsoft Project - Entering actual values in summary tasks

Posted on 2011-09-19
2
525 Views
Last Modified: 2013-12-19
Hi,
I'm currently working with the Earned Value functionality in Microsoft Project. I have set up a project plan with tasks and summary tasks and fixed the Baseline plan.

Question 1: How do I create deliverables without a project server? (in my example the deliverables equal the summary tasks, so ideally there should be a function that turns a summary task into a "trackable" deliverable)

Question 2: If I cannot create deliverables, how do I enter a manual value (eg. actual work, % physical progress) into a summary task field? I am aware that you can enter actual values on task level, but it is unrealistic to expect project members to state the % of completion and their hours burnt on task level. Therefore, is there a way to enter actuals into a summary task directly?

Thank you

0
Comment
Question by:bifi
2 Comments
 
LVL 18

Expert Comment

by:Richard Daneke
ID: 36579634

Question 1: How do I create deliverables without a project server?
  Please explain.  A Summary Task is a summary description of its subordinate tasks.  How is that a deliverable?
  Your view of the project can optionally show a restricted set of levels - summary tasks.
  Project is an Access database.  Task objects are available programmatically.

Question 2: is there a way to enter actuals into a summary task directly?
  By design, summary tasks are the sum of subordinate tasks.  This automatic calculation in Project is one is its key features.  Tasks can be updated in a variety of ways both individually and collectively.
0
 
LVL 4

Accepted Solution

by:
gcs001 earned 500 total points
ID: 36967640
Hi - coming in a bit late here - not sure if this question is still or open or not, but thought I'd give my 2 cents worth.

You don't mention which version of MSP you're using, so this could be tricky.
A good article to read regarding deliverable sin MSP can be found here:
http://msdn.microsoft.com/en-us/library/ms480428(v=office.12).aspx

Question 1: How do I create deliverables without a project server? (in my example the deliverables equal the summary tasks, so ideally there should be a function that turns a summary task into a "trackable" deliverable)
Answer: My suggestion would be to create a long-running task equal to the duration of the summary task (sum of all sub-tasks' durations).

Question 2: If I cannot create deliverables, how do I enter a manual value (eg. actual work, % physical progress) into a summary task field? I am aware that you can enter actual values on task level, but it is unrealistic to expect project members to state the % of completion and their hours burnt on task level. Therefore, is there a way to enter actuals into a summary task directly?
Answer: This long-running task can then be used for the project members to update their % complete, etc.  The downside of this, though, is that the other sub-tasks will not get any updates - unfortunately there is no way to auto-update the sub-tasks as you do not know which sub-task has which % completion ... unless the sub-tasks are equally split regarding duration, resources, etc.  then you could us a macro to average the "deliverables, long-running task" against the sub-tasks.

Hope this makes sense.
0

Featured Post

IT, Stop Being Called Into Every Meeting

Highfive is so simple that setting up every meeting room takes just minutes and every employee will be able to start or join a call from any room with ease. Never be called into a meeting just to get it started again. This is how video conferencing should work!

Join & Write a Comment

Article by: x-men
Where used to see Gantt charts for illustrating project timelines, but what if I wanted to visualize passed timed events? Here's how.
"Disruption" is the most feared word for C-level executives these days. They agonize over their industry being disturbed by another player - most likely by startups.
The purpose of this video is to demonstrate how to prevent comment spam on a WordPress Website. This will be demonstrated using a Windows 8 PC. Plugin Akismet will be used. Go to your WordPress login page. This will look like the following: myw…
The purpose of this video is to demonstrate how to set up the permalinks on a WordPress Website. This will be demonstrated using a Windows 8 PC. Go to your WordPress login page. This will look like the following: mywebsite.com/wp-login.php : Go t…

705 members asked questions and received personalized solutions in the past 7 days.

Join the community of 500,000 technology professionals and ask your questions.

Join & Ask a Question

Need Help in Real-Time?

Connect with top rated Experts

20 Experts available now in Live!

Get 1:1 Help Now