• Status: Solved
  • Priority: Medium
  • Security: Public
  • Views: 539
  • Last Modified:

Microsoft Project - Entering actual values in summary tasks

Hi,
I'm currently working with the Earned Value functionality in Microsoft Project. I have set up a project plan with tasks and summary tasks and fixed the Baseline plan.

Question 1: How do I create deliverables without a project server? (in my example the deliverables equal the summary tasks, so ideally there should be a function that turns a summary task into a "trackable" deliverable)

Question 2: If I cannot create deliverables, how do I enter a manual value (eg. actual work, % physical progress) into a summary task field? I am aware that you can enter actual values on task level, but it is unrealistic to expect project members to state the % of completion and their hours burnt on task level. Therefore, is there a way to enter actuals into a summary task directly?

Thank you

0
bifi
Asked:
bifi
1 Solution
 
Richard DanekeTrainerCommented:

Question 1: How do I create deliverables without a project server?
  Please explain.  A Summary Task is a summary description of its subordinate tasks.  How is that a deliverable?
  Your view of the project can optionally show a restricted set of levels - summary tasks.
  Project is an Access database.  Task objects are available programmatically.

Question 2: is there a way to enter actuals into a summary task directly?
  By design, summary tasks are the sum of subordinate tasks.  This automatic calculation in Project is one is its key features.  Tasks can be updated in a variety of ways both individually and collectively.
0
 
gcs001Commented:
Hi - coming in a bit late here - not sure if this question is still or open or not, but thought I'd give my 2 cents worth.

You don't mention which version of MSP you're using, so this could be tricky.
A good article to read regarding deliverable sin MSP can be found here:
http://msdn.microsoft.com/en-us/library/ms480428(v=office.12).aspx

Question 1: How do I create deliverables without a project server? (in my example the deliverables equal the summary tasks, so ideally there should be a function that turns a summary task into a "trackable" deliverable)
Answer: My suggestion would be to create a long-running task equal to the duration of the summary task (sum of all sub-tasks' durations).

Question 2: If I cannot create deliverables, how do I enter a manual value (eg. actual work, % physical progress) into a summary task field? I am aware that you can enter actual values on task level, but it is unrealistic to expect project members to state the % of completion and their hours burnt on task level. Therefore, is there a way to enter actuals into a summary task directly?
Answer: This long-running task can then be used for the project members to update their % complete, etc.  The downside of this, though, is that the other sub-tasks will not get any updates - unfortunately there is no way to auto-update the sub-tasks as you do not know which sub-task has which % completion ... unless the sub-tasks are equally split regarding duration, resources, etc.  then you could us a macro to average the "deliverables, long-running task" against the sub-tasks.

Hope this makes sense.
0

Featured Post

[Webinar] Kill tickets & tabs using PowerShell

Are you tired of cycling through the same browser tabs everyday to close the same repetitive tickets? In this webinar JumpCloud will show how you can leverage RESTful APIs to build your own PowerShell modules to kill tickets & tabs using the PowerShell command Invoke-RestMethod.

Tackle projects and never again get stuck behind a technical roadblock.
Join Now