Question about MS Project Resourcing Leveling

I have a MPP file that are not yet resource-leveled. Is it possible that if I let MS Project to do the leveling for me, the results may differ slightly when I do this, say, on different computers? I am just curious how such MS Project decides how to level the resources.

Thank you
0
ocan
Asked:
ocan
1 Solution
 
SANTABABYCommented:
It is mainly driven by the available units for the resources and the relative priority(1...1000, higher value indicates higher priority for the tasks) . I do not thik that levelling will vary from machine to machine.
Before you level, please make sure that you have resources assigned for tasks with appropriate %availability, dependencies between tasks are set , tasks are assigned right priority.
0

Featured Post

Free Tool: Site Down Detector

Helpful to verify reports of your own downtime, or to double check a downed website you are trying to access.

One of a set of tools we are providing to everyone as a way of saying thank you for being a part of the community.

Tackle projects and never again get stuck behind a technical roadblock.
Join Now