I would like to know how to do the following as a calculation  :
Basdically I  have 3 Tables
1.PRODUCT DATA
   Product ID
   Product Category
   Quantity to Be Produced
2.PRODUCTION RATES
   UNITS per Hour (Production Rate Per Product Category per Hour)
   fk Product Category
3 PRODUCTION DAY SET UP
    Production ID
     Hours to Produce
     Day Of Production
Hours to Produce Field to evaluate   a)The Product Category  of the Product Code then, b)Get the Rate Of Production (For this particular Category) and c) Divide the Quantity to be Produced by the Rate Of Production to give the number of Hours it will take to Produce this product on the selected Day Of Production.
Many Thanks
 
   
   
 
0
Krisraychris
Asked:
Krisraychris
1 Solution
 
North2AlaskaCommented:
The Day of Production in the PRODUCTION DAY SET UP table contains Monday, Tuesday, ... ?

No where do I see a way to select the Day of Production in the other tables.  I suspect you have not included the field in the Production Rates tables.  I'm I correct in assuming that Day Of Production also needs to be included in the Production Rates table?
0

Featured Post

Free Tool: Site Down Detector

Helpful to verify reports of your own downtime, or to double check a downed website you are trying to access.

One of a set of tools we are providing to everyone as a way of saying thank you for being a part of the community.

Tackle projects and never again get stuck behind a technical roadblock.
Join Now