Changing schedule of a cloned maintenance plan fails

I successfully exported the plans and imported them back in my server. I renamed the maintenance plan in the process, IMPORT-Full_Backup_Plan. The original name of the plan is Full_Backup_Plan.

However, when I try to schedule tbe "cloned" plan, I get this error:
Rename failed for Job Schedule 'Full_Backup_Plan Subplan_1'.
There are several subplans associated with this. Do I need to schedule the individual subplans first and then do the toplevel plan?

data_bitsdbaAsked:
Who is Participating?

[Product update] Infrastructure Analysis Tool is now available with Business Accounts.Learn More

x
I wear a lot of hats...

"The solutions and answers provided on Experts Exchange have been extremely helpful to me over the last few years. I wear a lot of hats - Developer, Database Administrator, Help Desk, etc., so I know a lot of things but not a lot about one thing. Experts Exchange gives me answers from people who do know a lot about one thing, in a easy to use platform." -Todd S.

AnujSQL Server DBACommented:
Exactly, you must start this from the sub-plans to the top level.
0

Experts Exchange Solution brought to you by

Your issues matter to us.

Facing a tech roadblock? Get the help and guidance you need from experienced professionals who care. Ask your question anytime, anywhere, with no hassle.

Start your 7-day free trial
It's more than this solution.Get answers and train to solve all your tech problems - anytime, anywhere.Try it for free Edge Out The Competitionfor your dream job with proven skills and certifications.Get started today Stand Outas the employee with proven skills.Start learning today for free Move Your Career Forwardwith certification training in the latest technologies.Start your trial today
Microsoft SQL Server 2005

From novice to tech pro — start learning today.