Go Premium for a chance to win a PS4. Enter to Win

x
?
Solved

Multiple Projects with Shared Activities Setup with MS Project 2012

Posted on 2012-03-27
4
Medium Priority
?
514 Views
Last Modified: 2012-03-29
I have a master project that has fundamentally two projects, but they share resources and more importantly, many of the same activities with many having the same duration and people.  What is the best way to set this up.  management wants to be able to see critical paths for both.  Basically I would start with 2 sub projects, but the shared activities, people and durations is what throws me.
0
Comment
Question by:avalonwgi
  • 2
4 Comments
 
LVL 12

Expert Comment

by:Dr. Thomas Henkelmann
ID: 37776642
Hi,

wouldn't it help if you create 3 and not only 2 subprojects? One for the common activities where you only have to maintain the activities and their duration once and also assign the resources only once with the COMBINED workload, and then 2 additonal projects with only the tasks relevant to these projects. If you link the tasks across the projects in the master project you will also get the overall critical path.

Regards

Thomas
0
 

Author Comment

by:avalonwgi
ID: 37776658
Yes, I gave that some thought.  Is it better to have a 3rd or just put the shared activities into the master project?  Also, because I haven't done this before, but if i link tasks in the master project do you lose the individual critical paths or does it just add the master critical path and still leaves the individuals still there?  Dave
0
 
LVL 18

Accepted Solution

by:
xtermie earned 2000 total points
ID: 37782642
Having the 3rd project with the common activities may create peculiar dependencies and may throw off the critical path of the two main sub projects.
Why dont you simply have the MASTER project, the TWO Subprojects and WITHIN the master project have the common tasks as Activities to which some of the other two sub projects tasks are linked and/or dependent upon them.

That way you won't lose the critical paths as well.  For the later part, just ensure that in Tools > Options, Calculation, you enable (check) "Calculate multiple critical paths" options.  This will allow Project to calculate the critical path for each chain (subproject) of tasks.
0
 

Author Closing Comment

by:avalonwgi
ID: 37784106
Thank you.
0

Featured Post

Prepare for your VMware VCP6-DCV exam.

Josh Coen and Jason Langer have prepared the latest edition of VCP study guide. Both authors have been working in the IT field for more than a decade, and both hold VMware certifications. This 163-page guide covers all 10 of the exam blueprint sections.

Question has a verified solution.

If you are experiencing a similar issue, please ask a related question

Ever wonder what it's like to get hit by ransomware? "Tom" gives you all the dirty details first-hand – and conveys the hard lessons his company learned in the aftermath.
In a use case, a user needs to close an opened report by simply pressing the Escape (Esc) key. This can be done by adding macro code in Report_KeyPress or Report_KeyDown event.
Visualize your data even better in Access queries. Given a date and a value, this lesson shows how to compare that value with the previous value, calculate the difference, and display a circle if the value is the same, an up triangle if it increased…
This lesson discusses how to use a Mainform + Subforms in Microsoft Access to find and enter data for payments on orders. The sample data comes from a custom shop that builds and sells movable storage structures that are delivered to your property. …

824 members asked questions and received personalized solutions in the past 7 days.

Join the community of 500,000 technology professionals and ask your questions.

Join & Ask a Question