Solved

Multiple Projects with Shared Activities Setup with MS Project 2012

Posted on 2012-03-27
4
492 Views
Last Modified: 2012-03-29
I have a master project that has fundamentally two projects, but they share resources and more importantly, many of the same activities with many having the same duration and people.  What is the best way to set this up.  management wants to be able to see critical paths for both.  Basically I would start with 2 sub projects, but the shared activities, people and durations is what throws me.
0
Comment
Question by:avalonwgi
  • 2
4 Comments
 
LVL 12

Expert Comment

by:thausla
ID: 37776642
Hi,

wouldn't it help if you create 3 and not only 2 subprojects? One for the common activities where you only have to maintain the activities and their duration once and also assign the resources only once with the COMBINED workload, and then 2 additonal projects with only the tasks relevant to these projects. If you link the tasks across the projects in the master project you will also get the overall critical path.

Regards

Thomas
0
 

Author Comment

by:avalonwgi
ID: 37776658
Yes, I gave that some thought.  Is it better to have a 3rd or just put the shared activities into the master project?  Also, because I haven't done this before, but if i link tasks in the master project do you lose the individual critical paths or does it just add the master critical path and still leaves the individuals still there?  Dave
0
 
LVL 18

Accepted Solution

by:
xtermie earned 500 total points
ID: 37782642
Having the 3rd project with the common activities may create peculiar dependencies and may throw off the critical path of the two main sub projects.
Why dont you simply have the MASTER project, the TWO Subprojects and WITHIN the master project have the common tasks as Activities to which some of the other two sub projects tasks are linked and/or dependent upon them.

That way you won't lose the critical paths as well.  For the later part, just ensure that in Tools > Options, Calculation, you enable (check) "Calculate multiple critical paths" options.  This will allow Project to calculate the critical path for each chain (subproject) of tasks.
0
 

Author Closing Comment

by:avalonwgi
ID: 37784106
Thank you.
0

Featured Post

Courses: Start Training Online With Pros, Today

Brush up on the basics or master the advanced techniques required to earn essential industry certifications, with Courses. Enroll in a course and start learning today. Training topics range from Android App Dev to the Xen Virtualization Platform.

Question has a verified solution.

If you are experiencing a similar issue, please ask a related question

Using Word 2013, I was experiencing some incredible lag when typing.  Here's what worked for me....
Technology opened people to different means of presenting information, but PowerPoint remains to be above competition. Know why PPT still works today.
The viewer will learn how to use a discrete random variable to simulate the return on an investment over a period of years, create a Monte Carlo simulation using the discrete random variable, and create a graph to represent the possible returns over…
The viewer will learn how to create two correlated normally distributed random variables in Excel, use a normal distribution to simulate the return on different levels of investment in each of the two funds over a period of ten years, and, create a …

785 members asked questions and received personalized solutions in the past 7 days.

Join the community of 500,000 technology professionals and ask your questions.

Join & Ask a Question