Solved

Microsoft Project Calculates 2 hours as .5 days and 4 hours as 1 day. Why?

Posted on 2012-04-11
2
695 Views
Last Modified: 2012-04-20
Hello All,

I think my questions may be a simple ones. I am creating a project plan with MS project. I am a beginner with project as ive used other tools in the past.

I have 8 hours set as one day and 40 hours set as one week. I also have my project set to display my duration column as hours not days. With all of this I have several issues:

-Even though I want to see duration in hours only, some rows dont recalculate in hours. They are stuck in days. How do I fix?

-Some work hours roll up to durations that arent accurate. So not only is it not just pushing the hours into the duration column, it is also calulating 2 hours as .5 days for example.

Another question is, why do some of my hours have a ? next to it?

Finally, is there a way to have project take my start and end dates, then take a guess at assigning my project to the work days in between my start and end?

Thanks in advance

-CH
0
Comment
Question by:daarchive
2 Comments
 
LVL 12

Accepted Solution

by:
thausla earned 500 total points
ID: 37836461
Hi,

this is many questions in one :)

The easy one first: the ? is always shown after entering a new task to indicate that the duration has been set to the default of 1day and is an estimated duration. As soon as you enter a duration, the ? goes away.

Have you set the Options..Schedule to show "Hours" for the duration? Be aware that there are 2 ways to set the option: "All new projects" or "Project1". If you choose "All new projects", the setting for "Hours" will apply to all tasks in all new projects which seems to be what you are looking for. However, any tasks that have been created with the "wrong" setting of "Days" will keep this setting unless they are summary tasks.

What do you mean by "Some work hours roll up to durations that arent accurate" ? Have you assigned resources to the tasks? Depending on the task type there is NO direct recalculation between work and duration, e.g. you can plan 10 hours of work during 5 days of duration (which is very common in scheduling).

The last part also leaves space for interpretation: do you want to set the project start date (yes, you do this in the "Project Information" window in the "Project" ribbon) and define the latest date for the project end? How should the tool "guess" what tasks you need?

Regards

Thomas
0
 
LVL 1

Author Closing Comment

by:daarchive
ID: 37870835
TY Thomas. Your explaination helped alot!
0

Featured Post

Enabling OSINT in Activity Based Intelligence

Activity based intelligence (ABI) requires access to all available sources of data. Recorded Future allows analysts to observe structured data on the open, deep, and dark web.

Join & Write a Comment

Communication between departments might not happen in two different languages, but they do exist in two different worlds. With different targets and performance goals the same phrase often means something completely different to each party. Learn ho…
Technology opened people to different means of presenting information, but PowerPoint remains to be above competition. Know why PPT still works today.
Viewers will learn how to maximize accessibility options in an Excel workbook for users with accessibility issues.
The viewer will learn how to use a discrete random variable to simulate the return on an investment over a period of years, create a Monte Carlo simulation using the discrete random variable, and create a graph to represent the possible returns over…

757 members asked questions and received personalized solutions in the past 7 days.

Join the community of 500,000 technology professionals and ask your questions.

Join & Ask a Question

Need Help in Real-Time?

Connect with top rated Experts

20 Experts available now in Live!

Get 1:1 Help Now