Microsoft Project Calculates 2 hours as .5 days and 4 hours as 1 day. Why?

Hello All,

I think my questions may be a simple ones. I am creating a project plan with MS project. I am a beginner with project as ive used other tools in the past.

I have 8 hours set as one day and 40 hours set as one week. I also have my project set to display my duration column as hours not days. With all of this I have several issues:

-Even though I want to see duration in hours only, some rows dont recalculate in hours. They are stuck in days. How do I fix?

-Some work hours roll up to durations that arent accurate. So not only is it not just pushing the hours into the duration column, it is also calulating 2 hours as .5 days for example.

Another question is, why do some of my hours have a ? next to it?

Finally, is there a way to have project take my start and end dates, then take a guess at assigning my project to the work days in between my start and end?

Thanks in advance

-CH
LVL 1
daarchiveAsked:
Who is Participating?
I wear a lot of hats...

"The solutions and answers provided on Experts Exchange have been extremely helpful to me over the last few years. I wear a lot of hats - Developer, Database Administrator, Help Desk, etc., so I know a lot of things but not a lot about one thing. Experts Exchange gives me answers from people who do know a lot about one thing, in a easy to use platform." -Todd S.

Dr. Thomas HenkelmannDirector Consulting ServicesCommented:
Hi,

this is many questions in one :)

The easy one first: the ? is always shown after entering a new task to indicate that the duration has been set to the default of 1day and is an estimated duration. As soon as you enter a duration, the ? goes away.

Have you set the Options..Schedule to show "Hours" for the duration? Be aware that there are 2 ways to set the option: "All new projects" or "Project1". If you choose "All new projects", the setting for "Hours" will apply to all tasks in all new projects which seems to be what you are looking for. However, any tasks that have been created with the "wrong" setting of "Days" will keep this setting unless they are summary tasks.

What do you mean by "Some work hours roll up to durations that arent accurate" ? Have you assigned resources to the tasks? Depending on the task type there is NO direct recalculation between work and duration, e.g. you can plan 10 hours of work during 5 days of duration (which is very common in scheduling).

The last part also leaves space for interpretation: do you want to set the project start date (yes, you do this in the "Project Information" window in the "Project" ribbon) and define the latest date for the project end? How should the tool "guess" what tasks you need?

Regards

Thomas
0

Experts Exchange Solution brought to you by

Your issues matter to us.

Facing a tech roadblock? Get the help and guidance you need from experienced professionals who care. Ask your question anytime, anywhere, with no hassle.

Start your 7-day free trial
daarchiveAuthor Commented:
TY Thomas. Your explaination helped alot!
0
It's more than this solution.Get answers and train to solve all your tech problems - anytime, anywhere.Try it for free Edge Out The Competitionfor your dream job with proven skills and certifications.Get started today Stand Outas the employee with proven skills.Start learning today for free Move Your Career Forwardwith certification training in the latest technologies.Start your trial today
Microsoft Applications

From novice to tech pro — start learning today.

Question has a verified solution.

Are you are experiencing a similar issue? Get a personalized answer when you ask a related question.

Have a better answer? Share it in a comment.