Solved

Microsoft Project Calculates 2 hours as .5 days and 4 hours as 1 day. Why?

Posted on 2012-04-11
2
696 Views
Last Modified: 2012-04-20
Hello All,

I think my questions may be a simple ones. I am creating a project plan with MS project. I am a beginner with project as ive used other tools in the past.

I have 8 hours set as one day and 40 hours set as one week. I also have my project set to display my duration column as hours not days. With all of this I have several issues:

-Even though I want to see duration in hours only, some rows dont recalculate in hours. They are stuck in days. How do I fix?

-Some work hours roll up to durations that arent accurate. So not only is it not just pushing the hours into the duration column, it is also calulating 2 hours as .5 days for example.

Another question is, why do some of my hours have a ? next to it?

Finally, is there a way to have project take my start and end dates, then take a guess at assigning my project to the work days in between my start and end?

Thanks in advance

-CH
0
Comment
Question by:daarchive
2 Comments
 
LVL 12

Accepted Solution

by:
thausla earned 500 total points
ID: 37836461
Hi,

this is many questions in one :)

The easy one first: the ? is always shown after entering a new task to indicate that the duration has been set to the default of 1day and is an estimated duration. As soon as you enter a duration, the ? goes away.

Have you set the Options..Schedule to show "Hours" for the duration? Be aware that there are 2 ways to set the option: "All new projects" or "Project1". If you choose "All new projects", the setting for "Hours" will apply to all tasks in all new projects which seems to be what you are looking for. However, any tasks that have been created with the "wrong" setting of "Days" will keep this setting unless they are summary tasks.

What do you mean by "Some work hours roll up to durations that arent accurate" ? Have you assigned resources to the tasks? Depending on the task type there is NO direct recalculation between work and duration, e.g. you can plan 10 hours of work during 5 days of duration (which is very common in scheduling).

The last part also leaves space for interpretation: do you want to set the project start date (yes, you do this in the "Project Information" window in the "Project" ribbon) and define the latest date for the project end? How should the tool "guess" what tasks you need?

Regards

Thomas
0
 
LVL 1

Author Closing Comment

by:daarchive
ID: 37870835
TY Thomas. Your explaination helped alot!
0

Featured Post

Is Your Active Directory as Secure as You Think?

More than 75% of all records are compromised because of the loss or theft of a privileged credential. Experts have been exploring Active Directory infrastructure to identify key threats and establish best practices for keeping data safe. Attend this month’s webinar to learn more.

Question has a verified solution.

If you are experiencing a similar issue, please ask a related question

Suggested Solutions

Title # Comments Views Activity
SCCM 2012 SP1 to SCCM SP2 upgrade 6 93
Access Convert Columns into Rows 5 60
Is AWS.RDS considered a part of "Big Data"? 4 93
Project Operations Manual 2 48
User Beware!  This is a rather permanent solution to removing your email from an exchange server.  The only way to truly go back is to have your exchange administrator restore your mailbox from backups.  This is usually the option of last resort.  A…
You can provide a virtual interface for remote stakeholders in a SWOT analysis through a Google Drawing template. By making real time viewing and collaboration possible, your team can build a stronger product.
Viewers will learn how to maximize accessibility options in an Excel workbook for users with accessibility issues.
The viewer will learn how to simulate a series of coin tosses with the rand() function and learn how to make these “tosses” depend on a predetermined probability. Flipping Coins in Excel: Enter =RAND() into cell A2: Recalculate the random variable…

943 members asked questions and received personalized solutions in the past 7 days.

Join the community of 500,000 technology professionals and ask your questions.

Join & Ask a Question

Need Help in Real-Time?

Connect with top rated Experts

9 Experts available now in Live!

Get 1:1 Help Now