APWIP-Admin
asked on
Microsoft Project 2013 Issues
I have a major issue. I exported data out of my project and accidentally checked it in to project server before check the data. All my resources got exported out so I am having to redo them. The problem I am running into is that now I am assigning resources and they are not getting allocated properly.
I have a user with only 45% available in an 8 hour day. That would make him only available 3.6 hours on any given day. He is scheduled for a task on one day for 4 hours. It is not spreading the task out over 2 days to complete. I am not sure how to fix it.
I have another situation where I have 2 resources only available 50% of an 8 hour day each. SO they can only spend 4 hours a day on this project. I have a set of tasks that they are both assigned to that would take 8 hours. It is showing the task being completed in 1 day because their is being split to 4 hours each on the task. The task will actually take 100% of both resources but they are only available 50% on any given day
I hope this makes sense to all of you. I am stuck as I need to get this project plan done first thing this morning. I am not sure why things are not calculating properly. I had them working fine yesterday but then I lost my work and now they are not.
I have a user with only 45% available in an 8 hour day. That would make him only available 3.6 hours on any given day. He is scheduled for a task on one day for 4 hours. It is not spreading the task out over 2 days to complete. I am not sure how to fix it.
I have another situation where I have 2 resources only available 50% of an 8 hour day each. SO they can only spend 4 hours a day on this project. I have a set of tasks that they are both assigned to that would take 8 hours. It is showing the task being completed in 1 day because their is being split to 4 hours each on the task. The task will actually take 100% of both resources but they are only available 50% on any given day
I hope this makes sense to all of you. I am stuck as I need to get this project plan done first thing this morning. I am not sure why things are not calculating properly. I had them working fine yesterday but then I lost my work and now they are not.
ASKER
Maybe I am not setting up the resource properly. I want to set my resource availability to work on a project. I do not want it to take the resource in the example above to be assigned 45% of the task. Let me know if I need to modify how I configure my resources.
ASKER CERTIFIED SOLUTION
membership
This solution is only available to members.
To access this solution, you must be a member of Experts Exchange.
ASKER
Not too sure what the issue is but thanks for helping.
ASKER
Rource-Example.jpg