Solved

Microsoft Project 2013 Issues

Posted on 2013-01-30
4
1,070 Views
Last Modified: 2013-02-05
I have a major issue.  I exported data out of my project and accidentally checked it in to project server before check the data.  All my resources got exported out so I am having to redo them.   The problem I am running into is that now I am assigning resources and they are not getting allocated properly.  

I have a user with only 45% available in an 8 hour day.  That would make him only available 3.6 hours on any given day.  He is scheduled for a task on one day for 4 hours.  It is not spreading the task out over 2 days to complete.  I am not sure how to fix it.

I have another situation where I have 2 resources only available 50% of an 8 hour day each.  SO they can only spend 4 hours a day on this project.  I have a set of tasks that they are both assigned to that would take 8 hours.  It is showing the task being completed in 1 day because their is being split to 4 hours each on the task.  The task will actually take 100% of both resources but they are only available 50% on any given day

I hope this makes sense to all of you.  I am stuck as I need to get this project plan done first thing this morning.  I am not sure why things are not calculating properly.  I had them working fine yesterday but then I lost my work and now they are not.
0
Comment
Question by:APWIP-Admin
  • 3
4 Comments
 

Author Comment

by:APWIP-Admin
ID: 38835357
Here is a sample of what I am talking about
Rource-Example.jpg
0
 

Author Comment

by:APWIP-Admin
ID: 38835468
Maybe I am not setting up the resource properly.  I want to set my resource availability to work on a project.  I do not want it to take the resource in the example above to be assigned 45% of the task.  Let me know if I need to modify how I configure my resources.
0
 
LVL 12

Accepted Solution

by:
thausla earned 500 total points
ID: 38844060
Hi,

looking at your screen shot it looks like you had Microsoft Project calculate the work and not let the resources drive the schedule as you expect it to happen.

Please try this and let me know if this what you are looking for:

- tasks should be set to "Auto scheduled" and "Fixed Work"
- after creating a new task, don't touch the duration field but enter the work you estimate for the task, e.g. 10 hours
- now, when you assign a resource with max units of 50%, Microsoft will schedule the task to run over TWO days, using the resource with the expected 50% per day
- if you have a second task running in parallel, Project DOES NOT automatically delay it. But if you click on "leveling options" in the "Resources" ribbon, you can set the leveling to "Automatic" and THEN the tasks will be delayed automatically to only run when the resources are available.

Concerning your "2 resource on one task" issue: if the task requires 8 hours and you have two people working 4 hours a day each, then the task can be done within one day. Right?

Regards

Thomas
0
 

Author Closing Comment

by:APWIP-Admin
ID: 38856531
Not too sure what the issue is but thanks for helping.
0

Featured Post

Is Your Active Directory as Secure as You Think?

More than 75% of all records are compromised because of the loss or theft of a privileged credential. Experts have been exploring Active Directory infrastructure to identify key threats and establish best practices for keeping data safe. Attend this month’s webinar to learn more.

Question has a verified solution.

If you are experiencing a similar issue, please ask a related question

Documentation is a big contentious issue in Agile. There is a reason for this. When you start your presentation on Agile you start by going through the 4 statements of agile manifesto (https://www.google.com/url?sa=t&rct=j&q=&esrc=s&source=web&cd=1&…
"Disruption" is the most feared word for C-level executives these days. They agonize over their industry being disturbed by another player - most likely by startups.
The viewer will learn how to simulate a series of coin tosses with the rand() function and learn how to make these “tosses” depend on a predetermined probability. Flipping Coins in Excel: Enter =RAND() into cell A2: Recalculate the random variable…
With the power of JIRA, there's an unlimited number of ways you can customize it, use it and benefit from it. With that in mind, there's bound to be things that I wasn't able to cover in this course. With this summary we'll look at some places to go…

911 members asked questions and received personalized solutions in the past 7 days.

Join the community of 500,000 technology professionals and ask your questions.

Join & Ask a Question

Need Help in Real-Time?

Connect with top rated Experts

23 Experts available now in Live!

Get 1:1 Help Now