Solved

Exclude, nights, weekends from date/time calculation

Posted on 2013-05-13
10
1,243 Views
Last Modified: 2013-05-15
Hello,
 
I need to calculate the time difference between 2 date/time columns.  The challenge is that I need to exclude evenings (after 5 p.m.), weekends (Saturday, Sunday) and U.S. Bank holidays. Is there a formula that I can plug into my existing formula to do this?

Please see the attached file and thanks in advance for all of your help!
Book-1.xls
0
Comment
Question by:angelfromabove
10 Comments
 
LVL 23

Expert Comment

by:tailoreddigital
Comment Utility
0
 
LVL 35

Expert Comment

by:[ fanpages ]
Comment Utility
Hi,

I need to calculate the time difference between 2 date/time columns.  The challenge is that I need to exclude evenings (after 5 p.m.), weekends (Saturday, Sunday) and U.S. Bank holidays. Is there a formula that I can plug into my existing formula to do this?

When does a morning "start" (if an evening commences at 5pm)?

BFN,

fp.
0
 

Author Comment

by:angelfromabove
Comment Utility
Let's just say that morning starts at 7:30 a.m. for these purposes.
0
 
LVL 50

Assisted Solution

by:barry houdini
barry houdini earned 125 total points
Comment Utility
Try listing your holiday dates in H2:H10 then use this formula in row 2

=(NETWORKDAYS(A2,B2,H$2:H$10)-1)*("17:00"-"7:30")+IF(NETWORKDAYS(B2,B2,H$2:H$10),MEDIAN(MOD(B2,1),"7:30","17:00"),"17:00")-MEDIAN(NETWORKDAYS(A2,A2,H$2:H$10)*MOD(A2,1),"7:30","17:00")

custom format as [h]:mm and copy down and you'll get the elapsed time in hours including just 07:30 to 17:00 on working days. Using that formula I get 766:01 for your last example

regards, barry
0
 

Author Comment

by:angelfromabove
Comment Utility
Perfect, thank you!  Can I just ask one more thing?

If the time value in the 2nd column of cells is blank, in other words the task is still in progress, I am getting ###### (pound signs) as the returned value.  Is there any way to say that if that cell is blank, to return the string "still in progress"?

Thanks!
0
Find Ransomware Secrets With All-Source Analysis

Ransomware has become a major concern for organizations; its prevalence has grown due to past successes achieved by threat actors. While each ransomware variant is different, we’ve seen some common tactics and trends used among the authors of the malware.

 
LVL 80

Assisted Solution

by:byundt
byundt earned 375 total points
Comment Utility
To trap a blank cell, just put barryhoudini's formula inside an IF statement:
=IF(B2="","still in progress",(NETWORKDAYS(A2,B2,H$2:H$10)-1)*("17:00"-"7:30")+IF(NETWORKDAYS(B2,B2,H$2:H$10),MEDIAN(MOD(B2,1),"7:30","17:00"),"17:00")-MEDIAN(NETWORKDAYS(A2,A2,H$2:H$10)*MOD(A2,1),"7:30","17:00"))
0
 

Author Comment

by:angelfromabove
Comment Utility
Great byundt, it worked!
0
 

Author Comment

by:angelfromabove
Comment Utility
Hi Barry, can you explain each component of the formula?

I will award the points and accept your solution shortly. I just want to make sure that I have a good understanding and I can explain it to someone..  For example, I don't know what Median and MOD are and what their function is in the formula?

Thanks!!!!
0
 
LVL 80

Assisted Solution

by:byundt
byundt earned 375 total points
Comment Utility
MOD(B2,1)      Divides B2 by 1, then returns the remainder (fractional part of the original number). Because time is the fractional part of a date/time serial number, MOD(B2,1) is a clever way of getting just the time part of B2.

MEDIAN picks the middlemost number in a set, so MEDIAN(MOD(B2,1),"7:30","17:00") would pick
7:30 if B2 is before 7:30
the actual time if B2 is between 7:30 and 17:00
17:00 if B2 is after 17:00

NETWORKDAYS returns the number of working days, from start through finish, but excluding weekends and holidays. If you start and finish on the same working day, then NETWORKDAYS returns 1, unless that day occurs on a weekend or holiday--in which case NETWORKDAYS returns 0.
NETWORKDAYS(A2,B2,H$2:H$10)-1)*("17:00"-"7:30")  is the number of working hours in those full workdays. You subtract 1 from NETWORKDAYS because you need to account for partial hours on start and finish days separately.

If B2 is on a weekend or holiday, then NETWORKDAYS(B2,B2,H$2:H$10) returns 0.
Likewise, if A2 is a weekend or holiday, then NETWORKDAYS(A2,A2,H$2:H$10) returns 0.
If either is a working day, then NETWORKDAYS returns 1.

IF(NETWORKDAYS(B2,B2,H$2:H$10),MEDIAN(MOD(B2,1),"7:30","17:00"),"17:00")
If B2 is a working day, then return MEDIAN(MOD(B2,1),"7:30","17:00"). Otherwise, return 17:00

MEDIAN(NETWORKDAYS(A2,A2,H$2:H$10)*MOD(A2,1),"7:30","17:00")
If A2 is a working day, then return MEDIAN(start time, 7:30, 17:00)
If A2 is not a working day, then MEDIAN(0, 7:30, 17:00) will return 7:30
0
 
LVL 80

Accepted Solution

by:
byundt earned 375 total points
Comment Utility
So if you put the three parts of the formula together:
Total number of working hours equals:
number of working hours assuming a full first day and ignoring the last day
plus working hours on last day until task ended
minus working hours on first day before task started

(NETWORKDAYS(A2,B2,H$2:H$10)-1)*("17:00"-"7:30")       number of working hours assuming a full first day and ignoring the final day

+IF(NETWORKDAYS(B2,B2,H$2:H$10),MEDIAN(MOD(B2,1),"7:30","17:00"),"17:00")    plus number of working hours on final day until task ended

-MEDIAN(NETWORKDAYS(A2,A2,H$2:H$10)*MOD(A2,1),"7:30","17:00"))   minus number of working hours on first day before task started
0

Featured Post

6 Surprising Benefits of Threat Intelligence

All sorts of threat intelligence is available on the web. Intelligence you can learn from, and use to anticipate and prepare for future attacks.

Join & Write a Comment

This article will show you how to use shortcut menus in the Access run-time environment.
Entering a date in Microsoft Access can be tricky. A typo can cause month and day to be shuffled, entering the day only causes an error, as does entering, say, day 31 in June. This article shows how an inputmask supported by code can help the user a…
Graphs within dashboards are meant to be dynamic, representing data from a period of time that will change each time the dashboard is updated with new data. Rather than update each graph to point to a different set within a static set of data, t…
This Micro Tutorial will demonstrate in Microsoft Excel how to add style and sexy appeal to horizontal bar charts.

762 members asked questions and received personalized solutions in the past 7 days.

Join the community of 500,000 technology professionals and ask your questions.

Join & Ask a Question

Need Help in Real-Time?

Connect with top rated Experts

11 Experts available now in Live!

Get 1:1 Help Now