How to create a Gantt chart in Crystal Reports 2008

Hi,
      I need to create two reports using Crystal Reports 2008 which have a Gantt chart each.

1) First report has a Gantt chart showing project timeline in weekly intervals for each month upto an year.

2) Second report has a Gantt chart showing project timeline in monthly intervals for 3 consecutive years.

Can anybody tell the procedure to create a Gantt chart using Crystal Reports 2008. I never created a Gantt chart using Crystal Reports and any help would be greatly appreciated.

Thanks in advance.
0
pradeepdevineni
Asked:
pradeepdevineni
1 Solution
 
mlmccCommented:
I have never built one and don't really have a database that would support one but here are the basic steps.

Open Crystal
Select your database
If you need the chart in a group then insert the group
Make the section you want the chart in tall enough to accept it (2-3 inches)
Click INSERT --> CHART
Drop the chart I the section
On the data tab change the ON CHANGE OF to FOR EACH RECORD
Click the TYPE Tab
Select the GANTT chart
Click the DATA Tab
Choose the START date
Choose the END date
Click OK

mlmcc
0
Question has a verified solution.

Are you are experiencing a similar issue? Get a personalized answer when you ask a related question.

Have a better answer? Share it in a comment.

Join & Write a Comment

Featured Post

Keep up with what's happening at Experts Exchange!

Sign up to receive Decoded, a new monthly digest with product updates, feature release info, continuing education opportunities, and more.

Tackle projects and never again get stuck behind a technical roadblock.
Join Now