DPM 2010 - Recovery Point Volime Threshold Exceeded

Hi,

I have come across a strange issue this morning with my DPM 2010 Server.

I use this to backup my Exchange 2010 environment. The retention range is set to 30 days which is fine but I have come in this morning and it seems the disks are full.

It looks like DPM has kept all of the data on there from day 1 of it running even though its only keeping a months worth of recovery points that I can restore back to.

My question is as follows,

Is there anyway of removing the old replicas or how can I set DPM to overwrite the old replicas?

Thanks,

Inf
inf_supportAsked:
Who is Participating?
 
Haresh NikumbhSr. Tech leadCommented:
check it out DPM2010  configuration For exchange 2010 step by step guide


http://www.msexchange.org/articles-tutorials/exchange-server-2010/management-administration/continuous-backup-exchange-server-2010-dpm-2012-part1.html


you need to check it out part 2, which shows how to configure retention policy  ( i hope you have not missed anything and also you can verify your configuration )
0
 
inf_supportAuthor Commented:
Hi,

Thank you.

This does help in the mean time but do you know if it is possible to set DPM to overwrite the old replicas?

I have 4 Hard Drive Arrays which each have 18TB on them.

I shouldn't be running out of space and it looks like to me the replicas are not being overwritten they are just being appended to.
0
Question has a verified solution.

Are you are experiencing a similar issue? Get a personalized answer when you ask a related question.

Have a better answer? Share it in a comment.

All Courses

From novice to tech pro — start learning today.