• Status: Solved
  • Priority: Medium
  • Security: Public
  • Views: 256
  • Last Modified:

Pasting Excel Data into Microsoft Projet

I'm desperately trying to paste data from an excel file into a Microsoft Project plan. Microsoft Project always seems to do some sort of calculations which is overriding the real data. For example :

Excel Source Data :
    Start     |Actual Work|Remaining Work|Actual Duration|Remaining Dur|  Finish |
11/26/13  |           5           |           20               |           2                |              1            |11/28/13 |

Once inserted into Microsoft Projet Data
    Start     |Actual Work|Remaining Work|Actual Duration|Remaining Dur|  Finish |
11/26/13  |      18.33         |         6.67              |           2                |              1            |11/28/13|

Task type is currently set to Fixed Work but I tried all sorts of trickery (all task types / manual vs auto shceduling) and it always does the same thing.

How to make this work? I realize the 20h in a single day, this is just an example. Bottom line is I want Project to trust the data and not override anything.

Thanks
0
STIWasabi
Asked:
STIWasabi
  • 3
  • 2
1 Solution
 
regmigrantCommented:
the changed information is because (probably) you are mixing the various tables project maintains when pasting the data. The Gantt chart view shows a mix of data from Task, Assignment, Resource, Calendar and when you past the mix project is trying to balance all the various elements.

It looks like you are trying to bring Actuals information into the sheet so you should setup all the tasks then swtich to view, table:tracking  and do the paste there.

However this can still be modified if your calendar and resources enforce any changes so turn off auto calculation and auto levelling until the paste is complete


If this doesn't work then a copy of the file(s) would help

Reg
0
 
STIWasabiAuthor Commented:
Attached a sample excel projet and the related project file (rename extension to mpp) into which I'd like to paste my excel projet data.

Please let me know, This is getting critical as I wasn't able to find a solution yet.

Thanks
MASTER.xlsx
MASTER.doc
0
 
regmigrantCommented:
apologies, I don't have access to that version of project during working hours, I will look at it later today

Reg
0
 
STIWasabiAuthor Commented:
Attached a 2000-2003 version, hoping it will react the same as my 2013 version.
MASTER-2003.doc
0
 
regmigrantCommented:
I think the problem is that your spread sheet has actual values summed on all outline levels - the summary figures have to be calculated by adding the lower levels together and rolling up.

Try with the attached where I  have cleared down the actuals from the summary tasks

Reg
MASTER1.xlsx
0
Question has a verified solution.

Are you are experiencing a similar issue? Get a personalized answer when you ask a related question.

Have a better answer? Share it in a comment.

Join & Write a Comment

Featured Post

Keep up with what's happening at Experts Exchange!

Sign up to receive Decoded, a new monthly digest with product updates, feature release info, continuing education opportunities, and more.

  • 3
  • 2
Tackle projects and never again get stuck behind a technical roadblock.
Join Now