Hi,

I have newbie type question.

Say if I have some tasks (1-5) where you have to complete task 1 before starting task 2, etc...

Say I am 30% through task 1 and I get tasked to stop work on task 1 and jump across to the new urgent task.  How should I handle this in MS Project?

I want to be in the position that the plan clearly shows the impact of stopping tasking 1?

(I am a complete novice on MS Project 2010)

Thanks.
0
Comment
Question by:andyw27
  • 2
  • 2
4 Comments
 
LVL 12

Expert Comment

by:thausla
Comment Utility
Hi,

if the work should happen in a defined order (as you describe it) the first step would definitely be to select all 5 tasks and link them. Also make sure you set the project start date in the "Project" ribbon in "Project Information".
If you want Project to calculate them please also set the tasks to "Task Mode"=Auto. Now you can set the progress to the first task by either double clicking it and set 30%, or by showing task details (from the View ribbon) and enter 30%, or by clicking on e.g. "25%" in the Task ribbon. Yes, sorry, there are so many ways in Project to achieve the same result :)

Now you need to "stop working" on task 1 and leave it at 25% (or 30%, doesn't matter). For your question above you would now track progress for task 2 AND set the start date to the first day where you worked on the task. This causes a "conflict" in the schedule (on purpose!) because task 1 is NOT finished but task 2 has started - no problem and Project can handle this very real situation.

Does this help?

Regards

Thomas
0
 

Author Comment

by:andyw27
Comment Utility
Hi Thomas,

Thanks this is a great starting point.  In your message does task 2 refer to the new urgent task?

Does the new 'urgent' task need to be inserted into the original hierarchy and linked?
0
 
LVL 12

Accepted Solution

by:
thausla earned 500 total points
Comment Utility
Ah, didn't get that that the "urgent task" is a new one but thought it's one of the five you initially setup. The basic story is the same:

- if the new "urgent" task has a logical sequence and needs to be done before thee EXISTING task2, then I would insert it between 1 and 2, and link to task 2.
- if the new "urgent" task is independent, then just add it below the 5 linked tasks and record your progress as you move forward.

An additonal recommendation: to reflect that time goes by, please set your project status date on a weekly base ("Project" ribbon) and then click on "Update Project", then "Reschedule uncompleted tasks to start after" and hit OK. This will reschedule and show all work that still needs to be done after the status date.
0
 

Author Comment

by:andyw27
Comment Utility
Thanks that great.
0

Featured Post

Threat Intelligence Starter Resources

Integrating threat intelligence can be challenging, and not all companies are ready. These resources can help you build awareness and prepare for defense.

Join & Write a Comment

Article by: x-men
Where used to see Gantt charts for illustrating project timelines, but what if I wanted to visualize passed timed events? Here's how.
Entering a date in Microsoft Access can be tricky. A typo can cause month and day to be shuffled, entering the day only causes an error, as does entering, say, day 31 in June. This article shows how an inputmask supported by code can help the user a…
This video shows and describes the main difference between both orientations in Microsoft Word. Viewers will understand when to use each orientation and how to get the most out of them.
Polish reports in Access so they look terrific. Take yourself to another level. Equations, Back Color, Alternate Back Color. Write easy VBA Code. Tighten space to use less pages. Launch report from a menu, considering criteria only when it is filled…

743 members asked questions and received personalized solutions in the past 7 days.

Join the community of 500,000 technology professionals and ask your questions.

Join & Ask a Question

Need Help in Real-Time?

Connect with top rated Experts

15 Experts available now in Live!

Get 1:1 Help Now