Solved

MS Project 2013: linked subproject must have task 5 complete for master project to start on task 6

Posted on 2014-02-17
4
1,265 Views
Last Modified: 2014-02-17
Hi everyone,

I have several projects on MS Project 2013 and a "Master" project where I have imported my subprojects.

Here's the issue:  I have several projects where I can't start one of the phases of the master projects until sub projects A, B, C, finish task 5.  After task 5 is complete on each of these projects, then the master project can start on task 6.

How do I show this on MS Project? The subprojects DO NOT need to be complete 100% for the master project to start on task 6 but each of them need to get to a certain point before the next task in the master project starts.

I hope this makes sense.  Thanks for your help!
0
Comment
Question by:dani gammon
  • 2
  • 2
4 Comments
 
LVL 19

Accepted Solution

by:
regmigrant earned 500 total points
ID: 39865439
in the master project show the tasks from the inserted sub project and drag/drop the dependency link in the way you would any other task. The predecessor column should show something like "<>\project name\4FS"

Is that not what you need?
0
 
LVL 5

Author Comment

by:dani gammon
ID: 39865473
Yes, this is exactly what I needed.  Thank you!

The Predecessor shows up as "Drive Location:\Folder\ProjectName.mpp\9

Is there a way to rename this or this because that's where it's pulling the information from?
0
 
LVL 19

Expert Comment

by:regmigrant
ID: 39865693
that should be the filename of the sub project, note that project isn't clever enough to track revisions if you save to a different filename or move it to a different folder.
0
 
LVL 5

Author Comment

by:dani gammon
ID: 39865699
I see.  Thanks for your help!
0

Featured Post

Free Tool: Site Down Detector

Helpful to verify reports of your own downtime, or to double check a downed website you are trying to access.

One of a set of tools we are providing to everyone as a way of saying thank you for being a part of the community.

Question has a verified solution.

If you are experiencing a similar issue, please ask a related question

This article will guide you to convert a grid from a picture into Excel format using Microsoft OneNote and no other 3rd party application.
Outlook Free & Paid Tools
The viewer will learn how to simulate a series of sales calls dependent on a single skill level and learn how to simulate a series of sales calls dependent on two skill levels. Simulating Independent Sales Calls: Enter .75 into cell C2 – “skill leve…
The viewer will learn how to  create a slide that will launch other presentations in Microsoft PowerPoint. In the finished slide, each item launches a new PowerPoint presentation and when each is finished it automatically comes back to this slide: …

789 members asked questions and received personalized solutions in the past 7 days.

Join the community of 500,000 technology professionals and ask your questions.

Join & Ask a Question