Solved

MS Project 2013: linked subproject must have task 5 complete for master project to start on task 6

Posted on 2014-02-17
4
1,243 Views
Last Modified: 2014-02-17
Hi everyone,

I have several projects on MS Project 2013 and a "Master" project where I have imported my subprojects.

Here's the issue:  I have several projects where I can't start one of the phases of the master projects until sub projects A, B, C, finish task 5.  After task 5 is complete on each of these projects, then the master project can start on task 6.

How do I show this on MS Project? The subprojects DO NOT need to be complete 100% for the master project to start on task 6 but each of them need to get to a certain point before the next task in the master project starts.

I hope this makes sense.  Thanks for your help!
0
Comment
Question by:dani gammon
  • 2
  • 2
4 Comments
 
LVL 19

Accepted Solution

by:
regmigrant earned 500 total points
ID: 39865439
in the master project show the tasks from the inserted sub project and drag/drop the dependency link in the way you would any other task. The predecessor column should show something like "<>\project name\4FS"

Is that not what you need?
0
 
LVL 5

Author Comment

by:dani gammon
ID: 39865473
Yes, this is exactly what I needed.  Thank you!

The Predecessor shows up as "Drive Location:\Folder\ProjectName.mpp\9

Is there a way to rename this or this because that's where it's pulling the information from?
0
 
LVL 19

Expert Comment

by:regmigrant
ID: 39865693
that should be the filename of the sub project, note that project isn't clever enough to track revisions if you save to a different filename or move it to a different folder.
0
 
LVL 5

Author Comment

by:dani gammon
ID: 39865699
I see.  Thanks for your help!
0

Featured Post

How your wiki can always stay up-to-date

Quip doubles as a “living” wiki and a project management tool that evolves with your organization. As you finish projects in Quip, the work remains, easily accessible to all team members, new and old.
- Increase transparency
- Onboard new hires faster
- Access from mobile/offline

Join & Write a Comment

This article will show you how to use shortcut menus in the Access run-time environment.
My experience with Windows 10 over a one year period and suggestions for smooth operation
The viewer will learn how to simulate a series of coin tosses with the rand() function and learn how to make these “tosses” depend on a predetermined probability. Flipping Coins in Excel: Enter =RAND() into cell A2: Recalculate the random variable…
The viewer will learn how to create a normally distributed random variable in Excel, use a normal distribution to simulate the return on an investment over a period of years, Create a Monte Carlo simulation using a normal random variable, and calcul…

744 members asked questions and received personalized solutions in the past 7 days.

Join the community of 500,000 technology professionals and ask your questions.

Join & Ask a Question

Need Help in Real-Time?

Connect with top rated Experts

13 Experts available now in Live!

Get 1:1 Help Now