Solved

MS Project 2013

Posted on 2014-12-20
8
147 Views
Last Modified: 2015-01-06
I am trying to use MS Project 2013 to manage my project. I'd like to know the best way to present the duration and automate the % complete column. This is what I have:
- server upgrade (1/12/14 - 2/12/14)
     -> server assessment (4hrs - 1/12/14)
     -> server documentation (4 hrs - 1/12/14
     -> server backup (3 hrs - 1/15/14)

I have a duration column, start, and finish. How would I present the hrs and cross reference with % complete.

I hope it makes sense what I am asking. Thanks
0
Comment
Question by:leblanc
  • 4
  • 4
8 Comments
 
LVL 48

Expert Comment

by:PortletPaul
Comment Utility
I'm afraid it makes no sense to me. Could you explain further please?
 1 summary; 3 tasks
0
 
LVL 1

Author Comment

by:leblanc
Comment Utility
Let say it will take 2 days for the server assessment, 2 hrs on 12/12 and 2 hrs on 12/13. How would I present that in MS Project? Also if i am done with my 2 hrs on 12/12, is it possible to have the % complete column update automatically to 50% (like in this case)? Thx
0
 
LVL 48

Assisted Solution

by:PortletPaul
PortletPaul earned 500 total points
Comment Utility
Dates that put the month first are weird, but I assume your mean
2014-Dec-12 2 hrs then 2014-Dec-13 2 hrs

2014-Dec-13 is a Saturday and by default that is a non-work day so I'll use the 11th and 12th but the actual dates aren't important to the principles of how to do this.

Your question seems to need planning of WORK  (not duration) which could be represented as:
2 hours work on the 11th and 2 hours work on the 12th

so you create a task
create a resource to perform the work
assign the resource to the task
arrange the views so that you have "Resource Usage" in the lower right;
this view allows you to type in the hours of work on a day, see below those highlighted hours were type in at those locations on the view
type in work on the days required

is it possible to have the % complete column update automatically to 50%
I truly don't understand
Are you assuming that the work is planned for the 11th and today is now after the 11th and therefore that MSP will auto-magically spread pixie dust on your file and update it for you?

How do you know that 2 hours of work was really performed on that task?
is it really 50% complete if 2 hours work is performed? (maybe it is easier or harder than planned?)

Keeping a project plan up to date and relevant is a Project Manager's responsibility - that's a person, not the software.
0
 
LVL 1

Author Comment

by:leblanc
Comment Utility
ok. So the duration is the number of days I will be working on a project, not the time I will spend on the task, Correct? If yes, then I understood incorrectly.

So this is how I did it. If my task takes 4 hours to get it done for 2 days, I input in the duration as 4 hrs instead of 2 days. But I am running into a problem because it does not list 4 hrs for those 2 days, it changed as 16 hrs. I am so confused.
0
How to run any project with ease

Manage projects of all sizes how you want. Great for personal to-do lists, project milestones, team priorities and launch plans.
- Combine task lists, docs, spreadsheets, and chat in one
- View and edit from mobile/offline
- Cut down on emails

 
LVL 48

Assisted Solution

by:PortletPaul
PortletPaul earned 500 total points
Comment Utility
"WORK" is not the same as "DURATION"

They are different concepts (and have different places for input or display)

If you expect to WORK on a task for 2 hours today and 2 hours tomorrow that is 4 hours of planned WORK.
The  DURATION is 2 days.

You really need an introductory tutorial or book it is well beyond the scope of a question/answer dialog.
0
 
LVL 1

Author Comment

by:leblanc
Comment Utility
Sorry for my ignorance. I am just trying to learn. Thanks
0
 
LVL 48

Accepted Solution

by:
PortletPaul earned 500 total points
Comment Utility
Please try this youtube:
Microsoft Project Tutorial - Work vs Duration

It uses these 3 terms that are defined as:duration-span-work.png
0
 
LVL 1

Author Comment

by:leblanc
Comment Utility
I guess I misunderstood the meaning of the summary task duration of MS Project. This sure is helpful. Thx
0

Featured Post

What Security Threats Are You Missing?

Enhance your security with threat intelligence from the web. Get trending threat insights on hackers, exploits, and suspicious IP addresses delivered to your inbox with our free Cyber Daily.

Join & Write a Comment

Suggested Solutions

In this article I will provide some simple productivity hacks that will help you use Google to specifically show results from any web site (Experts-Exchange.com in my example), with minimal effort in Chrome and Firefox. I've seen a common theme a…
This article describes how to use the Send to Mail Recipient command. The instructions apply generally to Office 2007 and later versions, but Microsoft® Word 2013 was used for the specific steps and figures.  What is Send to Mail Recipient? Send…
This video teaches the viewer how to align pictures around text while keeping the text properly aligned in the document.
The viewer will learn how to make their project stand out over others by learning how to change colors and shapes, add spaces, change directions, and add bullets to their charts.

763 members asked questions and received personalized solutions in the past 7 days.

Join the community of 500,000 technology professionals and ask your questions.

Join & Ask a Question

Need Help in Real-Time?

Connect with top rated Experts

13 Experts available now in Live!

Get 1:1 Help Now