Go Premium for a chance to win a PS4. Enter to Win

x
?
Solved

MS Project 2013 auto schedule duration

Posted on 2014-12-22
2
Medium Priority
?
328 Views
Last Modified: 2014-12-22
I am a bit confused on how MS Project calculates the duration for the auto schedule for a summary task. Attached is the snapshot of my tasks. For the summary task, it summarizes as 20.38 days from 1/19 to 2/16. But the duration for all the tasks adds up to 16 hrs. I was expecting 2 days or 16 hrs for the duration for the summary task.
Capture.JPG
0
Comment
Question by:leblanc
  • 2
2 Comments
 
LVL 49

Accepted Solution

by:
PortletPaul earned 2000 total points
ID: 40513811
DURATION is the measurement, in calendar units, between a start point and a completion point, but MSP (and most PM software) ignore non-work days when calculating duration.

So, if something starts January 19, and completes on February 16

Then "elapsed duration" is the days
 19, 20, 21, 22, 23, 24, 25, 26, 27, 28 29, 30 , 31
 +
1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16
 +
3 hours

for "duration" remove Saturdays/Sundays and then
 19, 20, 21, 22, 23,   26, 27, 28 29, 30
 +
   2, 3, 4, 5, 6,   9, 10, 11, 12, 13
 +
3 hours
= 20.38 Days

For example, let's say we had  3 tasks, each takes 1 hour. They ALL can be conducted in parallel.
|---------| task 1
|---------| task 2
|---------| task 3

A summary of those tasks is  1 hour
|---------| summary
|---------| task 1
|---------| task 2
|---------| task 3

IF those tasks cannot be done in parallel then the summary duration is much larger:
|-----------------------------| summary
|---------| task 1
          |---------| task 2
                    |---------| task 3

Open in new window

You CANNOT simply add durations to arrive at the duration of a summary task, you MUST consider the span between start and end.
not-16-hours.png
0
 
LVL 49

Assisted Solution

by:PortletPaul
PortletPaul earned 2000 total points
ID: 40513873
0

Featured Post

[Webinar] Cloud and Mobile-First Strategy

Maybe you’ve fully adopted the cloud since the beginning. Or maybe you started with on-prem resources but are pursuing a “cloud and mobile first” strategy. Getting to that end state has its challenges. Discover how to build out a 100% cloud and mobile IT strategy in this webinar.

Question has a verified solution.

If you are experiencing a similar issue, please ask a related question

If you are like me and like multiple layers of protection, read on!
Mailbox Corruption is a nightmare every Exchange DBA wishes he never has. Recovering from it can be super-hectic if not entirely futile. And though techniques like the New-MailboxRepairRequest cmdlet have been designed to help with fixing minor corr…
With the power of JIRA, there's an unlimited number of ways you can customize it, use it and benefit from it. With that in mind, there's bound to be things that I wasn't able to cover in this course. With this summary we'll look at some places to go…
Monitoring a network: why having a policy is the best policy? Michael Kulchisky, MCSE, MCSA, MCP, VTSP, VSP, CCSP outlines the enormous benefits of having a policy-based approach when monitoring medium and large networks. Software utilized in this v…

916 members asked questions and received personalized solutions in the past 7 days.

Join the community of 500,000 technology professionals and ask your questions.

Join & Ask a Question