How do i set up social pane on the task form and have it display the notes for the "Regarding"

How can I get the Social Pane (Activities, Notes, Posts) to display on the Task form and have it show notes, etc. for the "Regarding" field?
foxhelpAsked:
Who is Participating?
 
Feridun KadirConnect With a Mentor Principal ConsultantCommented:
I don't think so without resorting to custom development.
0
 
Feridun KadirPrincipal ConsultantCommented:
I don't think there is a way to do that without resorting to development.
The social pane control doesn't apply to activities.

You could create a Quick View form for the regarding field (but you need a Quick View form for each entity type that you might use in Regarding) that shows the Social Pane and then add that form to the task form.

However, I would suggest educating users to click on the Regarding field where they can see everything to do with the regarding record.
0
 
foxhelpAuthor Commented:
Thanks for the response but it looks like the Quick View form is only for viewing and I wanted to be able to see the activities and enter notes right from the task form for the contact.  Do you know if there is a way to link the notes and activities to the task?
0